Project team
A collaborative group of civic, architectural, and construction partners leads delivery of the Continental Coliseum, with owner’s representatives CAA ICON and local project managers ADG Blatt overseeing execution. MANICA Architecture leads the design, working alongside TVS as the Architect of Record, while Design Workshop shapes the surrounding public realm and local artist Matt Goad develops custom interior installations. The Flintco–Mortenson construction joint venture builds the physical structure, and Legends Global will handle day-to-day operations and stadium hospitality following its planned 2028 completion.
Read alsoChurchill Downs Announces $920M Expansion to Enhance Kentucky Derby Experience
Read alsoRaj Sports to Build $150M Dual Practice Facility for Portland Thorns and WNBA Expansion Team

Continental Coliseum Arena: Factsheet
Project Description
New downtown Oklahoma City $1 billion NBA arena and entertainment facility
Minimum 750,000 square foot building
AddressExisting site of Cox Convention Center (previous Myriad/Prairie Surf Studios)
New OKC Thunder Continental Coliseum Arena: Key Dates
Demolition bids dueMarch 5, 2025
Contractor selection (Mortenson–Flintco)March 11, 2025
Contractor award finalizedMarch 25, 2025
Demolition beginsMarch 31, 2025
Initial renderingsSummer 2025
Concept designs unveiledJuly 16, 2025
Demolition completion deadlineSeptember 30, 2025
Secondary demolition phaseDecember 2025
Site cleared and turnoverFebruary 12, 2026
Naming rights finalized (Continental Coliseum)March 24, 2026
Groundbreaking ceremonyMarch 26, 2026
Public art partner approvedJune 2026
Final structural design deadlineMid-2027
Substantial completion targetLate summer 2028
Opening targetOctober–November 2028
Operations backstop deadlineJune 2029
Design Team
Lead ArchitectsTVS (Atlanta) & Manica Architecture (Kansas City)
Design contract value$61.6 million
Read alsoThe FC Dallas Toyota Stadium: History and upcoming renovation
Funding Sources
Lead72-month, one-cent sales tax (post MAPS 4)
MAPS 4 contribution$70 million
Thunder ownership contribution$50 million
Impact
Thunder committed 25-year lease tenancy in Oklahoma City
Will be premier NBA and entertainment destination
Temporary homeTeam continues to play at Paycom Center