Project Fact Sheet
Project/frameworkMinor and Major Schemes Framework 5 (MMSF5)
Client/procuring authorityLeicestershire County Council, on behalf of Midlands Highway Alliance Plus (MHA+)
Estimated value£1 billion (approximately US$1.31 billion), excluding VAT
Duration8 years
Start dateJune 1, 2027
End dateMay 31, 2035
Sub-Lot 1A£250 million (approximately US$327 million)
Sub-Lot 1B£250 million (approximately US$327 million)
Lot 2£500 million (approximately US$654 million)
ScopeHighway improvements and maintenance, bridges, subways, culverts, retaining walls, town centre enhancements, drainage, canal works and waste management facilities
Participation deadlineJanuary 8, 2027, 12:00 noon UK time
Enquiry deadlineDecember 20, 2026, 12:00 noon UK time
Award decision expectedApril 1, 2027
Project Team
Leicestershire County Council– Procurement authority
Midlands Highway Alliance Plus (MHA+)– Regional local authority alliance and framework client organisation
Balfour Beatty– Existing MSF4 contractor
Galliford Try– Existing MSF4 contractor
John Sisk (Sisk)– Existing MSF4 contractor
Taylor Woodrow (originally Eurovia Infrastructure)– Existing MSF4 contractor