Project Factsheet: MTerra Solar
ProjectMTerra Solar — integrated solar PV and battery energy storage facility
LocationFive municipalities across Nueva Ecija and Bulacan, Philippines
Developer / ownerTerra Solar Philippines Inc. — a joint investment of MGEN Renewable Energy (via subsidiary SP New Energy Corporation, SPNEC) and Actis
OfftakerMeralco (Power Supply Agreement)
Phase 1 commercial operationsDeclared 26 August 2026 (600 MWac mid-merit; further 250 MWac to follow)
Grid approvalFinal Certificate of Approval to Connect (FCATC) issued by NGCP for 950 MWac solar and 825 MW BESS
Phase 1 energized capacity1,373 MWac solar PV and 825 MW / 3,300 MWh BESS
Full build-out3,500 MWp solar PV and 4,500 MWh BESS
Grid connection500 kV transmission line to the Nagsaag–San Jose Transmission Line
InvestmentActis US$600 million (Philippines’ largest greenfield infrastructure FDI to date)
Households servedApproximately 2.4 million
Emissions avoided4.3 million tonnes a year
TimelineGroundbreaking November 2024; Phase 1 inaugurated July 2026; Phase 1 commercial operations August 2026; Phase 2 expected 2027