Contractors have submitted their best and final offers for NEOM Oxagon infrastructure construction package in northwestern Saudi Arabia. The procurement advances essential utility networks, roads and public-realm infrastructure across NEOM’s industrial city. The latest tender covers wet and dry services, civil works and limited earthworks. However, NEOM has not disclosed the package’s estimated construction cost or individual bidders. The wider Oxagon development carries a reported net project value of approximately $49.3 billion. This figure covers the wider development, not the infrastructure contract under consideration.
The latest procurement highlights the importance of completing industrial infrastructure before additional manufacturing and logistics facilities enter operation. In particular, the package will provide essential connections between industrial assets and supporting utility networks. It also includes roads, pedestrian infrastructure, lighting, communications and security installations. Consequently, the contract represents an important step towards preparing Oxagon’s industrial districts for further development.
NEOM is developing Oxagon as an advanced industrial and logistics centre anchored by the operational Port of NEOM. The development occupies a strategic Red Sea location, connecting regional and international trade routes. According to NEOM, its core development area covers approximately 48 square kilometres. The industrial city targets renewable-energy manufacturing, advanced industries and artificial intelligence-driven businesses.
NEOM Oxagon infrastructure construction package covers extensive utility networks
The infrastructure package combines wet utility networks with electrical, telecommunications and other dry infrastructure installations. The wet infrastructure component includes potable water and firewater distribution networks. It also covers irrigation, domestic wastewater, industrial wastewater and stormwater systems.
Meanwhile, the dry infrastructure scope includes optional 33kV medium-voltage electrical networks. These connections will run from primary substation switchgear to designated asset interface points. The package also includes 230/400V low-voltage networks serving street and pedestrian lighting.
Furthermore, contractors must provide control networks, radio systems and smart-city infrastructure. The electrical scope also incorporates Saudi Electricity Company and information technology components. Pumping stations and other public-realm electrical loads form part of the package.
The telecommunications and security installations add another significant component. These include underground information and communications technology pathways and transmission containment systems. Contractors will also install security networks and service-provider connections. Additionally, the package includes Interior Ministry fibre networks.
Fibre-optic connections for Enowa power lines also form part of the works. The contractor will integrate instrumentation, control and automation packages for wet-services infrastructure. These systems will support monitoring and management of the utility networks.
NEOM Oxagon infrastructure construction package includes roads and landscaping
The civil engineering component covers roads, pavements and associated public-realm improvements. Contractors will install road furniture, signage and wayfinding infrastructure. Landscaping within the designated road right-of-way also forms part of the construction scope.
However, the package excludes construction of the main Highway 55 and demolition of the existing highway. Contractors will undertake only agreed crossings beneath Highway 55. They will also complete defined connections at approved interface points.
Similarly, bulk earthworks and rough grading fall outside this contract. Other contractors will undertake those activities before the appointed infrastructure contractor starts its work. The successful bidder will instead handle local trimming and excavation.
The remaining earthworks include trenching, backfilling and compaction. Contractors must prepare the affected areas to meet issued-for-construction finish levels. This division separates bulk site preparation from detailed utility and civil infrastructure installation.
NEOM Oxagon infrastructure construction works advance alongside transport tenders
The latest infrastructure procurement follows other construction and transport tenders across Oxagon. Notably, contractors have also submitted final offers for the Highway 55 upgrade. Its first phase covers approximately 14 kilometres of road, with two lanes in each direction. The design-and-build project also includes one bridge and three interchanges. NEOM expects the highway construction programme to take 22 months.
Highway 55 provides an important connection between the Red Sea coast and mainland northwestern Saudi Arabia. Currently, it provides the only north-south road connection between Duba and the NEOM region. The upgrade should improve cargo movement between Duba Port, Oxagon and other regional destinations.
Meanwhile, NEOM is advancing plans for a freight railway connecting the Port of NEOM with Saudi Arabia’s national rail network. Consultants submitted bids on October 31 for the railway’s concept design and feasibility studies. The proposed route will connect Oxagon with Saudi Arabia Railways’ North-South Railway at Al-Baseeta junction. The planned railway will extend more than 400 kilometres.
Water infrastructure procurement is also progressing within the industrial city. Enowa is procuring a separate industrial wastewater treatment facility with an initial capacity of 35,000 cubic metres daily. MEED estimates that facility could cost up to $165 million. Five contractors or bidding consortia submitted offers for that separate contract. These developments demonstrate the scale of utility and transport infrastructure required across Oxagon.
The successful infrastructure contractor will therefore contribute to the next stage of industrial site preparation. However, NEOM has yet to announce the preferred bidder, contract award or construction commencement date. The procurement outcome should clarify the delivery arrangements for the extensive utility and civil works.

Saudi Arabia is also expanding its industrial logistics capacity through major investments outside NEOM. The $218 million ASMO SPARK logistics hub in the Eastern Province has attracted additional contractor bids for its expansion. The development will add more than 124,000 square metres of logistics infrastructure at King Salman Energy Park. Both projects demonstrate the Kingdom’s growing investment in industrial facilities, integrated supply chains and infrastructure supporting Vision 2030.