Progress at UK's Liverpool Bay Carbon Capture Storage Project After €520M Saipem EPC Contract

The Liverpool Bay Carbon Capture and Storage (CCS) project, developed by Eni as the critical transport and storage backbone for the HyNet North West industrial decarbonization cluster, has reached significant milestones as it advances toward construction and operations. Following the UK government’s historic £21.7 billion funding commitment to regional carbon capture clusters in late 2024, Eni and the UK government reached financial close for the Liverpool Bay infrastructure in April 2025. Since then, major engineering, procurement, and construction (EPC) contracts have been mobilized. Key contractors, including United Living Energy and RSK Group, are actively working on environmental and archaeological mitigation ahead of major pipeline work. Construction of the onshore pipeline infrastructure is slated to run through June 2027, featuring a new 36-inch and 20-inch pipeline system designed to safely channel captured CO2 from heavy industries like Heidelberg Materials’ Padeswood cement plant.

The project’s financial and corporate footing has also strengthened considerably. In December 2025, Eni finalized a strategic partnership with Global Infrastructure Partners (GIP), divesting a 49.99% stake in Eni CCUS Holding. This was followed by a major financial boost in May 2026, when Eni CCUS Holding secured a new financing facility exceeding £500 million from international lenders to bolster its portfolio of CCS projects, including Liverpool Bay. Offshore, the development involves partially decommissioning legacy natural gas assets and installing new modules on the Hamilton Main, Hamilton North, and Lennox platforms to prepare them for carbon injection. With key environmental statements and storage permit reviews progressing through regulatory bodies, Eni is targeting late 2027 for the first injection of carbon dioxide. The first phase of the project aims to permanently store up to 4.5 million tonnes of CO2 per year in these depleted Irish Sea reservoirs, with plans to scale up to 10 million tonnes per year after 2030.

Similarly, projects like the Earlham Gigagrid contribute to powering UK data centers by delivering massive, dedicated, low-carbon electricity that entirely bypasses the nation’s severe onshore grid bottlenecks. By co-locating power generation directly at the energy source (like offshore gas fields) and abating emissions via Carbon Capture and Storage (CCS), these “islanded” solutions provide tech hyperscalers with the immediate, baseload power required for intensive AI workloads without straining the domestic consumer grid or sacrificing net-zero targets.

Eni and the UK government reached financial close for the Liverpool Bay infrastructure in April 2025.
Eni and the UK government reached financial close for the Liverpool Bay infrastructure in April 2025.

April 30, 2025

Italian oil and gas contractor, Saipem, has been awarded a €520 million contract by Eni for UK’s Liverpool Bay Carbon Capture Storage (CCS) project. The Engineering, Procurement and Construction (EPC) contract is for 3 years, by when the Liverpool CCS project will be complete. United Living Energy Limited was also awarded a 3 years £250 million contract. Their role has been described as a primary contractor for the Liverpool Bay CCS project.

Project factsheet

Owner: Liverpool Bay CCS Limited

Location: Liverpool Bay, UK

Developer: Eni

Project partners: Encyclis, EET Viridor, Heidelberg Materials, Progressive Energy

EPC contractor: Saipem

Saipem EPC contract cost: €520 million

Project start date: 2020

Current status: Construction

Start of construction: 2025

Project completion date: 2028

Saipem’s €520 Million EPC Contract and the Project’s Construction Phase

Saipem’s EPC contract for the CCS facility in Liverpool Bay is aimed at developing a compression station. This will involve the conversion of the existing gas compression and treatment facility at Point of Ayr, in north Wales into a CO2 compression station.

The electrical CO2 compression station will allow for permanent carbon storage in the Liverpool Bay area which currently houses depleted offshore sites. Additionally, the €520 million EPC contract will also include development in both offshore and onshore segments of the Liverpool Bay CCS compression station.

Progress at UK's Liverpool Bay Carbon Capture Storage Project After €520M Saipem EPC Contract
Liverpool Bay Carbon Capture Storage network sits in the HyNet North West Industrial Decarbonisation Cluster, one made up of industries in the North West of England and North Wales

Saipem’s EPC contract for the development of the Liverpool Bay CCS compression station will also include project commissioning. This will feature assistance to commissioning of the new facility in 2028.

The project’s construction phase will also include changes to parts of the offshore platforms, as well as 149km of onshore and offshore pipelines. Also included in the construction plans is the installation of 35km of new pipelines to connect industrial CO2 emitters to the Liverpool Bay CCS network. These emitters include cement manufacturers, waste plants, and low-carbon hydrogen producers, among others.

The Liverpool Bay Carbon Capture Storage (CCS) Project

Eni, an energy company driven by a philosophy to support “socially fair energy transition” globally, runs the Liverpool Bay Transport and Storage infrastructure.

Liverpool Bay Carbon Capture Storage network sits in the HyNet North West Industrial Decarbonisation Cluster. The cluster is made up of industries in the North West of England and North Wales.

Upon CO2 transport to the carbon capture storage facility in the Liverpool Bay area, the green-house undergoes changes, among them compression, before storage. Storage in Liverpool’s HyNet CCS cluster is done in the depleted natural gas reservoirs lying offshore.

Progress at UK's Liverpool Bay Carbon Capture Storage Project After €520M Saipem EPC Contract
The CO2 compression station will allow for permanent CO2 storage in offshore depleted fields under Liverpool Bay. Currently, the UK has a target of storing up to 30 million tons of CO2 by 2030

Benefits of the Liverpool Bay CCS Project

The project is driven by two main objectives. These are achieving Net Zero and supporting the UK’s economic growth. The Liverpool Bay CCS facility will also make the HyNet North West one of the world’s first low-emission industrial clusters. The industrial cluster is also one of the UK’s most energy-intensive manufacturing districts.

Also read: Matrix’s Eccles and Kilmarnock BESS projects in Scotland, England to foster UK energy transition

Net Zero Goal By 2030

Since the CCS project inception in October of 2020, the project has seen tremendous progress. This also includes the government granted permission to transport CO2 in March 2024. Currently, the UK has a target of storing up to 30 million tons of CO2 by 2030. This initiative is plainly underscored by the government’s £21.7 million pledge to support the development of CCS projects in the UK in October last year.

Currently, the Liverpool Bay CCS facility is in its initial phase with an initial target capacity of 4.5 million tons per annum (MTPA). This number is expected to increase to 10 MTPA after 2030. In the long-run, this will effectively lead to the storage of a maximum of 190 metric tons (MT) of CO2.

Economic Support

The CCS project is in itself geared towards economic development. This is achieved by the investments channeled to the transport and storage of CO2. This then creates another chain of new jobs in the thousands, which the project developer, Eni, puts at 2,000 in the construction phase alone.

The EPC project by Saipem will also use more than 1,000 local resources during the construction phase. This was also emphasized by Eni less than a week ago after the project reached financial closure, and marking the start of the construction phase.

Project Team

Project Owners and Joint Venture Partners:

  • Eni (via Liverpool Bay CCS Limited): As the 100% owner and operator of the Liverpool Bay CO2 Transportation and Storage (T&S) infrastructure, Eni is the lead developer. They are managing the transition of legacy natural gas assets in the Irish Sea into permanent carbon storage sites.
  • Global Infrastructure Partners (GIP / part of BlackRock): In late 2025, GIP finalized a strategic partnership with Eni, acquiring a 49.99% stake in Eni CCUS Holding. They serve as the primary institutional investment partner co-funding the project’s development.

Engineering, Procurement, and Construction (EPC) Partners:

  • United Living Energy: Appointed in April 2025 as one of the primary contractors tasked with constructing and installing the onshore CO2 pipeline network.
  • RSK Group: Providing critical environmental, geotechnical, and archaeological mitigation services ahead of the pipeline’s construction.
  • NRL Recruitment & Orion Group: The designated talent acquisition partners managing the complex staffing requirements for civil engineering, pipeline construction, and offshore mechanical engineering.

Founding Industrial Emitters (HyNet Partners):

  • Heidelberg Materials: Directing captured emissions from their Padeswood cement plant.
  • EET (Essar Energy Transition): Providing emissions from the Stanlow Manufacturing Complex.
  • Viridor and Encyclis: Connecting waste-to-energy facilities to the network.
  • Progressive Energy: Managing the regional low-carbon hydrogen transition that links back to the network.

Financial Advisors and Legal Lead Partners:

  • BNP Paribas: Served as the sole financial advisor helping Eni CCUS Holding secure its landmark £500+ million financing facility in May 2026.
  • Latham and Watkins: The lead legal counsel advising the consortium of 13 international lenders (including NatWest, ING, and MUFG) on project financing and development matters.

Also read: Microsoft Invests in AtmosClear’s Carbon Capture Facility in Louisiana with World’s Largest Deal

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.