Delta Forge 1 Campus: $300M Loan Backs $3.6B Louisiana Build

Home » Buildings » Data Center » Delta Forge 1 Campus: $300M Loan Backs $3.6B Louisiana Build
Delta Forge 1 campus

The Delta Forge 1 campus has secured fresh construction money. On November 23, Applied Digital said it closed a $300 million senior secured bridge facility to fund the campus in Rapides Parish, Louisiana. The loan helps fund a $3.6 billion AI data center already under construction.

How the $300 million loan works

The facility is a delayed-draw term loan with a 364-day maturity. It pays interest at the Secured Overnight Financing Rate plus 300 basis points. A leading global financial institution is the lender, though the company did not name it. The project’s assets secure the loan, and Applied Digital can repay it at any time without a premium.

Money is not available all at once. Draws depend on construction milestones, state approval of electricity rates, lender consents, and financial covenants. Therefore, regulatory approvals directly affect how fast the funds flow.

What Delta Forge 1 will include

The campus is planned for 430 MW and sits on about 300 acres in Boyce, near Alexandria. Louisiana announced the $3.6 billion project in May. It will initially hold two facilities totalling 300 MW of critical IT load. Cleco will supply power, and the design uses closed-loop cooling. Site work began in January, and initial operations are expected in mid-2027. The state expects about 200 direct jobs and more than 1,000 construction jobs at the peak. In addition, a US-based, high-investment-grade hyperscaler has pre-leased the campus.

Why more financing is still needed

Applied Digital says it will seek more funding to finish the campus. It expects to complete the remaining project financing for Delta Forge 1 and Polaris Forge 3 in the first quarter of 2027, followed by Delta Forge 2 in the second quarter. The bridge loan therefore covers construction until that longer-term financing arrives.

How this fits Applied Digital’s pipeline

On the same day, the company announced a separate $5.4 billion, 18-year lease for 150 MW with a tier-one hyperscaler. That brings its contracted base-term lease revenue above $41 billion. Delivery of that capacity is expected to begin in the first half of 2028.

The company is also delivering capacity elsewhere. On November 24, it brought the first 25 MW at Polaris Forge 2 in Harwood, North Dakota, to ready for service.

Delta Forge 1 campus
Delta Forge 1 sits near Alexandria, in central Louisiana.

What happens next?

The next steps are state approval of electricity rates, the first loan draws, and further construction. Watch also for the Q1 2027 project financing and for the first operations in mid-2027.

Other projects

Basin Electric has selected PCL Industrial as general contractor for North Dakota’s largest power plant, the Bison Generation Station. The plant is a new $4 billion natural gas-fired power plant in Williams County, North Dakota. The scope of the project represents one of the largest investments ever undertaken by Basin Electric. Furthermore, it advances Basin’s ambition to provide reliable, dispatchable power to meet growing traditional-load demands.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *