The Gateway Development Commission (GDC) has launched the second tunnel boring machine (TBM) for the $16 billion Hudson Tunnel Project, beginning excavation of the southern tube and bringing both new rail tunnels into the underground construction phase in New Jersey.
The second machine began mining on November 18, following the launch of the first TBM in October. Together, the machines will excavate the first 5,100 feet of the twin tunnel tubes through the Palisades, connecting the tunnel portal in North Bergen with the Hudson County Access Shaft on the border of Weehawken and Hoboken.
The milestone puts both new tunnel tubes under construction simultaneously. However, excavation beneath the Hudson River remains a subsequent phase of the project.
GDC estimates that the first tunneling section will take approximately one year to complete, including scheduled maintenance stops. Once the machines reach the Hudson County Access Shaft, crews will remove them and introduce a second pair of TBMs designed to handle the mixed ground conditions beneath the Hudson River.

Two tunnel boring machines advance through the Palisades
The first machine, which began mining in October, has already excavated approximately 400 feet of the northern tube and installed more than 60 tunnel lining rings.
Each machine will install nearly 850 rings, assembled from more than 5,000 precast concrete segments, to form the permanent tunnel lining as excavation progresses.
The two machines are single-shield TBMs designed for tunneling through the hard, dry rock formations of the Palisades. Each has a 28-foot, 8-inch-diameter cutterhead and trailing gantries extending approximately 500 feet. The complete machine weighs more than 1,680 tons.
Their excavation systems combine rock removal and tunnel construction in one operation. Rotating disc cutters break the rock into smaller pieces, which collecting buckets direct onto a conveyor system for removal from the tunnel.
Behind the cutterhead, an erector arm positions precast concrete segments to form the tunnel lining. Hydraulic thrust jacks then push against the completed lining to advance the machine.
GDC’s three commissioners, Alicia Glen, Balpreet Grewal-Virk and Tony Coscia, described the second launch as another step toward delivering a modern and more reliable regional rail system.
GDC Chief Executive Officer Tom Prendergast also emphasized that the first machine’s October launch was only the beginning of the tunneling operation, with the second machine bringing both new tubes into active excavation.
Hudson River crossing will require a different set of machines
The Palisades tunneling work represents the first stage of excavation for the new rail connection between New Jersey and Manhattan.
After completing the initial 5,100-foot section, the machines will be removed through the Hudson County Access Shaft. A second pair of TBMs will then take over construction of the approximately 7,250-foot Hudson River Tunnel Section, extending from the shaft in New Jersey to the 12th Avenue Access Shaft in Manhattan.
Unlike the first machines, which are optimized for hard rock, the second pair will be designed to operate through varying underground conditions, including rock and soft soil.
The river crossing also requires additional ground preparation. GDC expanded its Hudson River Ground Stabilization contract to include removing approximately 500 wooden piles buried in the riverbed that could obstruct the future TBMs.
The commission’s Fall 2026 construction update reported that approximately 1,000 feet of riverbed, more than 100 feet wide, had already undergone stabilization work.
The Hudson River Tunnel Section also includes nine cross-passages connecting the two new tubes, alongside work to stabilize ground near Hudson-Bergen Light Rail tracks and reinforce the foundations of the Willow Avenue Bridge between Weehawken and Hoboken.

Contractors advance separate construction packages
The Hudson Tunnel Project is divided into 10 construction packages covering the new tunnel infrastructure, connections to existing rail lines and rehabilitation of the existing North River Tunnel.
The first stretch of tunnel boring and construction of the Hudson County Access Shaft fall under the Palisades Tunnel Project. Schiavone Lane Dragados JV is leading construction, while the Port Authority of New York and New Jersey manages project delivery in partnership with GDC.
The subsequent Hudson River Tunnel Section is being delivered by Traylor/Walsh/Skanska JV under a separate construction contract awarded in April 2026.
The Manhattan Tunnel and New Jersey surface alignment are also being advanced through separate construction packages, reflecting the scale of work required to connect the new tunnels to the existing rail network and New York Penn Station.
$16B project targets 2035 opening
The Hudson Tunnel Project will provide a new two-track passenger rail connection between New Jersey and Manhattan while allowing the existing North River Tunnel, which entered service in 1910, to undergo comprehensive rehabilitation.
The existing tunnel was severely damaged by Hurricane Sandy in 2012 and remains a source of maintenance work and potential service disruptions along the Northeast Corridor.
The new tunnel is targeted to enter service in 2035, with rehabilitation of the existing North River Tunnel expected to finish in 2038.
The project has an estimated construction budget of approximately $16 billion and is supported by federal funding commitments and contributions from New York, New Jersey and regional transportation partners.
Funding uncertainty previously threatened construction after federal disbursements were suspended in October 2025. Work paused at several sites in February 2026 before resuming following the release of withheld federal payments.
With both Palisades TBMs now operating, the project has moved into a more visible phase of underground construction. The next major milestone will be completing the New Jersey drives and transitioning to the more technically demanding excavation beneath the Hudson River.

Hudson Tunnel Project factsheet
- Project: Hudson Tunnel Project
- Estimated project budget: $16 billion
- Owner and delivery authority: Gateway Development Commission
- Location: New York and New Jersey, USA
- Current milestone: Second TBM launched for southern tunnel tube
- First tunneling section: Approximately 5,100 feet through the Palisades
- First TBM launch: October 2026
- Number of TBMs: Four across two tunneling phases
- Palisades Tunnel contractor: Schiavone Lane Dragados JV
- Hudson River Tunnel contractor: Traylor/Walsh/Skanska JV
- Palisades construction manager: Port Authority of New York and New Jersey
- New tunnel opening target: 2035
- Existing North River Tunnel rehabilitation target: 2038