SOSA Energy Center Secures $78M Financing for 150 MW Texas Battery Storage Project

Home » Energy » Battery Storage » SOSA Energy Center Secures $78M Financing for 150 MW Texas Battery Storage Project

Project Factsheet

Project NameSOSA Energy Center (SOSA BESS)

LocationMadison County, Texas (ERCOT North market)

Capacity150 MW / 300 MWh (2-hour duration battery energy storage system)

Total InvestmentApproximately $100 million

Financing Package$78 million non-recourse construction and bridge financing (backed by an $80 million committed preferred equity takeout at completion and a draw on the OIC preferred facility)

Construction StatusBegan Q4 2025; civil works and substation installation are complete, with major equipment deliveries next

Expected Commercial Operation Date (COD)Q3 2027

Revenue ModelMerchant operation in ERCOT North, with flexibility for future contracted offtake agreements

Local Economic ImpactExpected to create 65 construction jobs and generate $9.3 million in tax revenue for Madison County and North Zulch ISD over 10 years

Project Team

  • Owner & Operator: Energy Vault Holdings, Inc. (via its Asset Vault platform and project entity SOSA Energy Center, LLC)
  • EPC Contractor (Engineering, Procurement & Construction): Energy Vault (self-performing EPC)
  • Original Project Developer: Savion, LLC (a Shell plc subsidiary, which sold the development rights to Energy Vault in October 2025)
  • Administrative & Collateral Agent (Bridge Lender): First-Citizens Bank & Trust Company
  • Preferred Equity / Strategic Institutional Partner: Orion Infrastructure Capital (OIC)

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *