Project Factsheet
ProjectABI-1 Electric Generating Unit
Developer and operatorVoltaGrid LLC
LocationShackelford County, near Abilene, Texas, United States
Regulatory milestoneAir quality construction and operating permit issued November 19, 2026
Total authorized generating capacity2,582 MW
Previous permitted configuration210 engines / 709 MW
Total authorized engines620 four-stroke lean-burn natural gas reciprocating engines
Engine breakdown250 Jenbacher J620 units (3.22 MW each) and 370 Jenbacher J624 units (4.80 MW each)
Plant configuration10 independently operating power blocks with 60-to-90-second standby ramp capability
Supporting equipment60 natural gas fuel heaters, 20 diesel black-start engines, 10 lube-oil tanks, and urea storage tanks
Offtake customerVantage Data Centers (Frontier campus)
Associated data center investment$25 billion (backed by Vantage, DigitalBridge, and Silver Lake)
Data center capacity1.4 GW across 10 buildings (3.7 million square feet on 1,200 acres)
Projected data center workforceMore than 5,000 workers across construction and operations
Permitted annual greenhouse-gas limit10,627,597 tons of carbon dioxide equivalent (10.62 million tons of CO₂)
Permitted annual criteria pollutants569.6 tons NOx, 917.6 tons CO, and 523.1 tons VOCs
Pollution controlsSelective catalytic reduction (98% NOx efficiency) and oxidation catalysts (95% CO and VOC efficiency)
Permit validity conditionsConstruction must begin within 18 months with no hiatus exceeding 18 months; Title V operating permit application required prior to startup