The Gabal El Zeit wind farm project in Egypt has advanced towards a new phase of private-sector ownership and operation. This follows the signing of US$420 million investment, operation and power purchase agreements between Alcazar Energy, the New and Renewable Energy Authority (NREA) and the Egyptian Electricity Transmission Company (EETC) in June 2026.

Under the agreements, Alcazar Energy will acquire, operate and manage the existing 580MW wind farm complex in the Red Sea Governorate. This will be done through a locally established project company. Alcazar will also do routine upgrades to maintain the wind farm’s generation capacity at a minimum of 580MW throughout the contract period. This is while undertaking a separate 500 MW renewable energy project also in the Ras Ghareb region, the Niat and Rasgha wind farms.

The Gabal El Zeit wind farm project comprises three wind farms with capacities of 240MW, 220MW and 120MW. Further progress emerged in September 2026 when the International Finance Corporation (IFC) disclosed that it was considering providing up to US$120 million in debt financing towards the acquisition, operation and maintenance of the facility. A projected board consideration date of November 30, 2026 was also set.

Gabal El Zeit Wind Farm in Egypt Advances Under $420 Mn Alcazar Energy Deal

Additionally, the IFC financing remains pending approval. It is not yet a confirmed disbursement. Siemens Gamesa Renewable Energy currently operates and maintains the wind farms. The company is also expected to remain involved following the acquisition. However, the exact scope and duration of its future maintenance arrangements are still under negotiation. The Egyptian Electricity Transmission Company will also purchase the electricity from the Gabal El Zeit wind farm. This will be under a 25-year power purchase agreement guaranteed by Egypt’s Ministry of Finance.

Gabal El Zeit Wind Farm Project Fact Sheet

Location: Gabal El Zeit, Red Sea Governorate

Geographical setting: Eastern Desert, along the Gulf of Suez

Project type: Onshore wind power generation

Total installed capacity: 580MW

Number of wind farms: 3

Individual capacities: 240MW, 220MW and 120MW

Original project owner: New and Renewable Energy Authority (NREA), Egypt

New investor and operator: Alcazar Energy Partners III SLP

Transaction value: Approximately US$420 million

Estimated total project cost in IFC disclosure: Up to US$460 million

Proposed IFC financing: Up to US$120 million

Additional IFC financing instrument: Interest rate swap of up to US$10 million

Electricity purchaser: Egyptian Electricity Transmission Company (EETC)

Power purchase agreement: 25 years

PPA guarantee: Egyptian Ministry of Finance

Existing wind farm operator: Siemens Gamesa Renewable Energy

Future operations and maintenance: Siemens Gamesa expected to remain involved, with contractual arrangements under negotiation

Acquisition scope: Acquisition, operation, maintenance and upgrading of the three existing wind farms

Planned asset-life extension: 10 years

Development program: Egyptian state-owned asset privatization program

Environmental classification: IFC Category A

Project status: Acquisition and financing process. IFC financing also pending approval as of its September 2026 disclosure

IFC projected board consideration: November 30, 2026

Gabal El Zeit Wind Farm in Egypt: Project Overview

Reported February 15, 2023 – The Gabal El Zeit Wind Farm is a 100 square kilometer new wind farm situated in the Gabal El Zeit region, south of Ras Gharib city. In terms of area, turbine count, and power output, the station is among the most extensive electricity-generating facilities in the world. The wind farm features 300 turbines.

The wind farm has a generating capacity of 580 MW. The first phase has 120 turbines with a capacity of 240 MW. Gabal El Zeit wind farm’s second phase includes 110 turbines with a capacity of 220 MW, connecting 75 turbines with a capacity of 150 MW to the grid.

One hundred turbines were previously connected to the national electricity grid. The third project involves 60 under-construction turbines with a total of 120 MW. Gabal El Zeit wind farm costs about 12 billion pounds.

The station has a system for tracking migratory birds. It uses radar to shut down the turbines when the birds fly and restart them. This is a brand-new system. The Spanish firm “Gamesa” implemented the station before it merged with the German firm “Siemens.”

It has three administrative buildings, including one that houses the control center and monitors all the turbines operating simultaneously.

Read Also: Latvia’s Kurzéme Offshore wind farm to start operating before 2030

Over US$ 1bn worth of wind power plants are to be completed in Egypt within 3 years

Wind farm

Reported September 2014 – A network of wind power farms, with 600 megawatts will be set up in Egypt in three years. This is according to Egyptian Vice President Wael Hamdy. El Sewedy Electric, which is the company planning to build the farms, will start measuring wind speeds, assessing key environments, and carrying out topographic studies in relation to the wind power plants project.

Elsewedy Electric was named in July as the winner of the state tender. The company will set up six wind power plants in Egypt, each with about 100MW.

The Gebel El-Zeit wind energy project is expected to be part of Egypt’s government to increase renewable energy in the country. In March this year, Egypt’s Ministry of Electricity and Energy set out an agenda to add 20% of renewable energy into its national grid by 2020. This includes 12% from wind and 8% from hydraulic and solar energy.

The Gebel El-Zeit wind energy project may also increase the participation of the private sector in energy generation. The Egyptian Government is also commitment is to have the private sector contribute 67% of the wind farms by 2020. This is according to the set-out plan.

The vice president of Egypt also revealed that the Gebel El-Zeit wind power plants project will cost over US$1 billion.

The Gebel El-Zeit wind power plants project will be detrimental to Egypt’s plan to break away from reliance on gas-generated power. The country has also been hit by an energy crisis.

The government has also announced a plan to cut subsidies programs and support renewables. This is alongside recent plans to tender renewable power generation projects to help generate 8Gw of power in the country.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *