Project Factsheet
LocationNear Skwentna, Matanuska-Susitna (Mat-Su) Borough, Alaska.
Capacity1.25 GW (Gigawatts)
Investment$1 Billion initial agreement (Part of a larger $4 billion project scope)
Main DeveloperTerra Energy Center Corp (subsidiary of Flatlands Energy / Asia Alaska)
Operational DateEstimated 2030
Project StatusPre-FEED stage; Final Investment Decision (FID) expected in 2026.
Project Team
Terra Energy Center Corp (TECC)The primary project owner and developer.
Korate Asset Management (KOREIT)A prominent South Korean private equity and asset management firm that committed $500 million in equity investment in March 2026.
U.S. Department of Energy (DOE)Providing technical oversight and being petitioned for a $400 million clean energy grant under carbon capture funding initiatives.
Alaska Energy Authority (AEA)The state corporation coordinating with the developers to integrate the plant into the Alaska Railbelt grid.
Hyundai Heavy Industries Power Systems (HPS)The South Korean industrial giant signed an in-principle agreement in March 2026 to supply the plant’s high-efficiency, coal-fired boilers.
Sargent & LundyA world-leading engineering firm acting as the primary technical consultant for the power plant design and the integration of Carbon Capture and Storage (CCS) systems.
University of Alaska Fairbanks (UAF)Engaged in collaborative research regarding local coal quality and carbon sequestration viability.
AIDEA (Alaska Industrial Development and Export Authority)Leading the development of the West Susitna Industrial Access Road, which is the critical 100-mile corridor required to reach the plant site.
Matanuska Electric Association (MEA)Has been in close coordination with Terra Energy regarding a potential Power Purchase Agreement (PPA) to distribute the electricity to local consumers.
Alaska Department of Transportation (DOT&PF)Involved in the planning and expedited permitting of the public-access portions of the road infrastructure.