US$6.9 Bn Investment in S-Oil Shaheen Project Adds 3.2Mtpa Petrochemical Output in South Korea

Home » Energy » Crude Oil Refinery » US$6.9 Bn Investment in S-Oil Shaheen Project Adds 3.2Mtpa Petrochemical Output in South Korea

Project Fact Sheet

ProjectShaheen Petrochemical Complex

LocationOnsan National Industrial Complex, Ulsan, South Korea

Project typeIntegrated petrochemical production complex

Owner and developerS-Oil Corporation

Major shareholderSaudi Aramco

InvestmentKRW 9.258 trillion (approximately US$6.9 billion)

Site areaApproximately 880,000 square metres

Steam cracker capacity1.8 million tonnes of ethylene annually

Total additional petrochemical capacityApproximately 3.2 million tonnes annually

Technology UsedThermal Crude-to-Chemicals (TC2C)

Major facilitiesTC2C unit, steam cracker and polymer production plants

Main productsEthylene, propylene, butadiene and polyethylene

Construction startMarch 2023

Construction completionNovember 2026

Commercial operationsPlanned for 2027

Project purposeExpand petrochemical production, diversify S-Oil’s business and strengthen South Korea’s domestic feedstock supply

Project Team

S-Oil Corporation:Project owner, developer and operator.

Saudi AramcoS-Oil’s largest shareholder and strategic investment partner; co-developer of the TC2C technology.

Hyundai Engineering & ConstructionLead construction consortium member.

Hyundai Engineering:Main construction consortium participant.

Lotte Engineering & ConstructionConstruction consortium participant.

DL E&C:Contractor for the TC2C and interconnection construction package.

Lummus Technology:Co-developer of the TC2C technology with Saudi Aramco.

SABICExport marketing partner for polyethylene products.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.