Zeevonk offshore wind farm in Netherlands selects Siemens Gamesa for turbine supply

Home » Energy » Wind power » Zeevonk offshore wind farm in Netherlands selects Siemens Gamesa for turbine supply
Zeevonk Offshore Wind Farm

The Zeevonk offshore wind farm in the Netherlands has selected Siemens Gamesa as preferred partners for its wind turbine supply package. The development is part of the Netherlands’ wider offshore renewable energy programme and aims to expand clean electricity generation in the North Sea.

The selection marks an important step in advancing the Zeevonk Offshore Wind Farm project towards construction. In addition, it strengthens cooperation between major offshore wind developers and energy companies in delivering large-scale renewable energy infrastructure.The agreement covers 69 offshore wind turbines.

Siemens Gamesa turbine supply contract

Under the agreement, Siemens Gamesa will supply 69 SG 15-236 offshore wind turbines. Each turbine has a base capacity of 15MW, giving the first phase an installed capacity of more than 1GW. The turbines can also achieve a power boost of up to 15.5MW.

The turbines will feature a direct-drive design and a rotor diameter of 236 metres. Each blade measures approximately 115 metres. These specifications are intended to support electricity generation at the offshore site while improving turbine performance.

In addition to equipment supply, Siemens Gamesa has secured a separate service and warranty agreement. The scope includes long-term maintenance, operational support and turbine monitoring. This arrangement will support equipment availability throughout the operational period.

The selected turbines will also incorporate technologies aimed at reducing their environmental footprint. These include GreenerTower, which uses lower-emission steel in tower construction. Furthermore, RecyclableBlade technology allows blade materials to be separated and recycled at the end of their service life.

The turbines will also use RecyclableCoolingLiquid, which contains 93% recycled glycol. These measures support the project’s circularity objectives and efforts to reduce the environmental impact of offshore wind infrastructure.

Zeevonk Offshore Wind Farm

Manufacturing and installation schedule

Manufacturing of the turbines is planned for 2028, with offshore installation scheduled for 2029. The installation package has already been awarded to DEME, which will use its next-generation jack-up installation vessel, Norse Energi, to transport and install the 69 turbines.

DEME’s involvement follows an earlier contract covering the transportation and installation of 69 monopile foundations. The company will therefore undertake two major offshore construction packages for the first phase.

Meanwhile, EEW Special Pipe Constructions (EEW SPC) has secured the contract to manufacture the 69 monopile foundations. The foundations will use a transition-piece-less design, which allows turbine towers to connect directly to the monopiles.

Dutch cable manufacturer TKF will supply approximately 162 kilometres of 66kV inter-array cables. Boskalis has also secured the cable installation package. Together, these contracts establish important parts of the project’s supply and installation chain.

Zeevonk offshore wind project development

Zeevonk is being developed by Vattenfall and CIP through their joint venture. The project is located in the Dutch North Sea, approximately 63 to 84 kilometres off the coast near Bergen aan Zee.

The wider development is planned in two phases. Phase I will deliver approximately 1GW of offshore wind capacity by 2029. Phase II is scheduled for 2032 and will add another 1GW of wind capacity and 500MW of system integration capacity.

The second phase will also include an electrolyser at the Port of Rotterdam. The facility will use renewable electricity from the offshore wind farm to produce green hydrogen for industrial and other energy consumers.

Furthermore, the project is intended to improve the integration of offshore wind electricity into the Dutch energy system. Combining wind generation with hydrogen production and system integration infrastructure will provide additional options for using renewable electricity.

Zeevonk is being developed within the IJmuiden Ver Beta offshore wind area, which will also host the 2GW IJmuiden Ver Gamma-A and Gamma-B projects. Vattenfall and CIP secured the development rights in the Dutch offshore wind tender in 2024. The project subsequently adopted a phased development approach to align its construction schedule with the availability of supporting hydrogen transport infrastructure.

Project financing and energy supply

The development also has an established commercial route for part of its future electricity generation. Google signed a 15-year power purchase agreement (PPA) for 250MW of electricity from Zeevonk in 2024.

The agreement provides a long-term electricity offtake arrangement and supports the project’s commercial development. It also demonstrates the role of corporate renewable energy procurement in supporting large-scale offshore wind investments.

However, the Zeevonk offshore wind farm project remains subject to a final investment decision (FID). The turbine supply agreement and other major construction contracts represent progress towards implementation, but final project investment approval is still required.

Zeevonk Offshore Wind Farm

Zeevonk Offshore Wind Farm: Project Fact Sheet

Location: Dutch North Sea, Netherlands

Project type: Offshore wind energy development

Total planned capacity:2GW

Phase I capacity: Approximately 1GW

Phase II capacity: Approximately 1GW of wind and 500MW of system integration capacity

Project owners/developers: Vattenfall and Copenhagen Infrastructure Partners (CIP)

Turbine supplier: Siemens Gamesa

Turbine model: SG 15-236

Number of turbines:69 for Phase I

Individual turbine capacity: 15MW, with power boost capability up to 15.5MW

Foundation supplier: EEW Special Pipe Constructions

Inter-array cable supplier: TKF

Cable installation contractor: Boskalis

Turbine and foundation installation contractor: DEME

Manufacturing target:2028

Phase I installation target:2029

Phase II target: 2032

Project status: Development and procurement; awaiting final investment decision

Zeevonk Offshore Wind Farm:Project Team

Vattenfall: Joint project developer and owner.

Copenhagen Infrastructure Partners: Joint project developer and investor.

Siemens Gamesa: Wind turbine supplier and long-term service provider.

DEME: Responsible for foundation and turbine transportation and installation.

EEW Special Pipe Constructions:Manufacturer of the 69 monopile foundations.

TKF:Supplier of approximately 162 kilometres of inter-array cables.

Boskalis:Responsible for inter-array cable installation.

Google: Corporate electricity offtaker under a 250MW, 15-year PPA.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *