1.5GW Elementl Power Nuclear Power Plant in Ohio Advances with PJM Filing, GE Vernova Reactor Deal

Home » Energy » Nuclear » 1.5GW Elementl Power Nuclear Power Plant in Ohio Advances with PJM Filing, GE Vernova Reactor Deal
Elementl Power Nuclear Power Plant in Ohio

Project Overview

  • Capacity: 1.5GW
  • Location: Letart Township, Ohio
  • Developer: Elementl Power
  • Technology: GE Vernova Hitachi BWRX-300 SMR
  • Status: Grid interconnection filed

Scope

  • Nearly 700-acre project site
  • First 600MW submitted to PJM
  • Early Works Agreement signed
  • Privately financed development
  • Land acquisition underway

Project Highlights

  • Uses BWRX-300 SMR technology
  • Supports long-term energy security
  • Follows PJM’s new interconnection process
  • Expands U.S. nuclear generation capacity

Key Approvals

  • PJM interconnection review pending
  • NRC license required
  • Ohio Power Siting Board approval needed
  • Also final investment decision outstanding

Timeline

  • PJM review expected this year
  • Construction could begin in 2030
  • First unit targeted for 2034
  • Also additional phases planned thereafter

Outlook

  • Marks a key milestone for the project
  • Adds to the growing BWRX-300 pipeline
  • Regulatory approvals remain critical
  • Could strengthen Ohio’s clean energy supply

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *