Poland Advances $50 Billion Nuclear Power Plant With New Equipment Procurement Steps

Home » Energy » Nuclear » Poland Advances $50 Billion Nuclear Power Plant With New Equipment Procurement Steps
Poland Advances $50 Billion Nuclear Power Plant With New Equipment Procurement Steps

Poland is advancing procurement preparations for its first nuclear power station, with state-owned developer Polskie Elektrownie Jądrowe (PEJ) and the Westinghouse-Bechtel consortium taking further steps to secure long-lead components for the planned three-reactor development.

The latest progress centres on a letter of intent signed on November 19, 2026, by PEJ and the US consortium. The agreement establishes a framework for extending the scope of their Engineering Development Agreement to cover additional procurement activities for components needed for the plant’s first reactor.

The development is part of preparations for the approximately $50 billion project at Lubiatowo-Kopalino, in Poland’s Pomerania region along the Baltic Sea coast. The plant is planned to use three Westinghouse AP1000 reactors, with a combined generating capacity of approximately 3,750 megawatts.

Under the arrangement, Westinghouse and Bechtel will work with PEJ to advance procurement of long-lead items and support discussions with export credit agencies on financing for component supplies. The early procurement approach is intended to secure manufacturing capacity for equipment that can take years to produce and help reduce the risk of construction delays.

Latest agreements

The latest agreement builds on procurement activities initiated in October, when PEJ authorised Westinghouse to begin ordering six key components for the first reactor’s nuclear island. These include the reactor containment vessel and associated structural modules.

Four Polish manufacturers have since received conditional purchase orders from Westinghouse for prefabricated structural module work. They are Energomontaż-Północ Gdynia, FAMAK, Mostostal Kielce and Mostostal Kraków. Their respective scopes cover sections of the reactor-building wall and floor modules.

The orders remain conditional, and the manufacturers must first meet the applicable nuclear quality-assurance requirements before proceeding with full manufacturing and delivery of the components. PEJ and its partners will finalize the remaining production and delivery arrangements through subsequent procurement steps.

Japanese engineering company IHI Corporation has also received an order from Westinghouse for engineering and procurement activities covering long-lead items for a reactor containment vessel and an associated large steel module for the first unit.

Alongside equipment procurement, negotiations are continuing on the project’s main Engineering, Procurement and Construction (EPC) contract. PEJ and the Westinghouse-Bechtel consortium agreed the main commercial terms in September 2026, but the full contract has not yet been signed.

The Wall Street Journal, citing Dow Jones reporting, said the parties now expect to sign the EPC agreement by the end of the first quarter of 2027, later than the previous target of the end of 2026. The project’s overall construction and commissioning timetable is still being maintained, according to the reporting.

Preparatory work

Preparatory work is also progressing at the Lubiatowo-Kopalino site. Bechtel assumed site management in August 2026, with early activities including grading and levelling, drainage works, temporary access roads and geological investigations. These activities are preparing the site for the main nuclear construction phase.

PEJ submitted its application for a nuclear construction permit to Poland’s National Atomic Energy Agency in March 2026. The company plans to submit a separate building permit application in 2027. The project targets the placement of its first nuclear concrete in the fourth quarter of 2028, subject to regulatory approvals and construction preparations.

The three reactors will enter commercial operation in stages, with the first expected in 2036, the second in 2037 and the third in 2038. Once all three units begin operating, the plant could supply approximately 10% of Poland’s electricity demand, helping the country diversify its energy mix and strengthen long-term energy security.

Poland’s planned nuclear power station is emerging as part of a much broader international expansion of nuclear infrastructure. The World Nuclear Association reported in November 2026 that approximately 80 reactors were under construction worldwide, with around 120 more planned. Countries including China, India, Egypt, Türkiye and Bangladesh are advancing reactor projects, while established nuclear markets are also pursuing new investment and extending existing capacity.

In Japan, TEPCO’s ongoing work at the Kashiwazaki-Kariwa Nuclear Power Station illustrates another side of this expansion: upgrading safety infrastructure to support the return of existing reactors. Together, these developments demonstrate how the global nuclear build-out involves not only new power stations such as Poland’s, but also substantial investment in the infrastructure supporting existing nuclear fleets.

Poland is advancing procurement preparations for its first nuclear power station
Poland is advancing procurement preparations for its first nuclear power station

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *