TEPCO Reviews Kashiwazaki-Kariwa Nuclear Facility Schedule After Construction Problems

Home » Energy » Nuclear » TEPCO Reviews Kashiwazaki-Kariwa Nuclear Facility Schedule After Construction Problems
TEPCO reviews construction schedules at Kashiwazaki-Kariwa Nuclear Power Station after concrete issues and contractor delays.

Tokyo Electric Power Company (TEPCO) is reviewing the construction schedule for safety facilities at its Kashiwazaki-Kariwa Nuclear Power Station in Japan after construction issues prompted its contractor to request changes to the work programme.

In a disclosure dated November 26, 2026, TEPCO said the construction schedule for the Specific Major Accident Response Facilities serving Units 6 and 7 would be reviewed, including their planned completion dates. The company said a revised schedule had not yet been determined.

TEPCO identified uneven concrete finishing in sections of the facilities’ principal structures as one of the construction issues. The contractor responsible for the main structures had also requested a review of the construction work and its schedule.

The disclosure followed reporting by Bloomberg that construction had encountered a concrete-strength problem affecting the facility associated with Unit 7. According to the report, the contractor expected the work to require an extension of more than a year.

The delay is significant because completion of the facilities is a regulatory requirement for the affected reactors. These structures are designed to provide additional protection against severe accidents, including deliberate aircraft impacts, and form part of Japan’s post-Fukushima nuclear safety requirements.

Unit 7

Unit 7 had previously been scheduled to complete its facility by August 2029, while the corresponding facility for Unit 6 had a September 2031 target. TEPCO has not formally confirmed replacement completion dates. Bloomberg reported that TEPCO executive Takeyuki Inagaki had indicated an aim to complete the Unit 7 facility by April 2031.

The construction review adds uncertainty to the timeline for Unit 7’s return to service. Although Unit 6 has returned to commercial operation, Unit 7 remains out of operation, and the completion of its required safety facility is an important condition in the station’s wider restart programme.

The Kashiwazaki-Kariwa station, located in Niigata Prefecture, is one of the world’s largest nuclear power stations by installed capacity. Its restart has been closely watched as Japan seeks to increase nuclear power generation and reduce reliance on imported fossil fuels.

TEPCO’s construction schedule review comes at a time when nuclear power is regaining momentum across several regions. From Europe’s plans for new generating capacity to Asia’s expanding reactor construction programmes, governments are increasingly treating nuclear energy as part of their long-term electricity and energy-security strategies. Poland’s planned Lubiatowo-Kopalino Nuclear Power Plant, a three-reactor development involving Westinghouse and Bechtel, is one example of this renewed investment. While Poland is preparing a new nuclear facility, Japan’s challenge at Kashiwazaki-Kariwa highlights the equally important task of completing safety upgrades needed to bring existing reactors back into operation.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *