$15bn Vantage Data Centers Lighthouse Campus Nears 25% Completion in Wisconsin

Home » Buildings » Data Center » $15bn Vantage Data Centers Lighthouse Campus Nears 25% Completion in Wisconsin
Vantage Data Centers Lighthouse Campus

Project Overview

  • Project Value: $15 billion
  • Location: Port Washington, Wisconsin
  • Developer: Vantage Data Centers
  • Status: Roughly 20%–25% complete

Scope

  • Four data center buildings
  • Also about 2.5 million square feet combined
  • Closed-loop cooling systems
  • Space for Oracle and also OpenAI

Project Highlights

  • Building toured: about 550,000 square feet
  • Also largest building: 759,000 square feet
  • 2,800–3,000 workers on site daily

Key Developments

  • Foundation pours began January 2026
  • Structural steel finished May 2026
  • Also first handovers expected late 2027

Key Challenges

  • Coordinating four general contractors
  • Managing phased handovers during construction
  • Also supporting a large daily workforce

Outlook

  • Buildings will be delivered in phases
  • Completed sections may also operate before entire buildings are finished

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *