2.9 GW Hornsea 3 Offshore Wind Farm; Seaway7 Readies Inter-Array Cable Installation off Norfolk, UK

Home » Energy » Wind power » 2.9 GW Hornsea 3 Offshore Wind Farm; Seaway7 Readies Inter-Array Cable Installation off Norfolk, UK
2.9 GW Hornsea 3 Offshore Wind Farm; Seaway7 Readies Inter-Array Cable Installation off Norfolk, UK

Project Overview

  • Project Name: Hornsea 3 Offshore Wind Farm
  • Developer and Operator: Ørsted
  • Co-owner: Apollo managed funds (50 percent), with Mubadala Investment Company investing alongside the Apollo led consortium
  • Location: North Sea, about 120 kilometers off the Norfolk coast, UK
  • Capacity: 2.9 GW
  • Turbines: 197 Siemens Gamesa SG 14-236 DD turbines, rated at 14 MW excluding power boost
  • Foundations: 197 XXL monopiles, averaging 1,670 metric tons and 90 meters each
  • Grid Connection: Two offshore HVDC converter stations, export cables and an interlink cable of about 350 kilometers combined, and an onshore converter station at Swardeston, Norfolk
  • Inter-Array Cables: 192 cables rated at 66 kV, about 500 kilometers in total
  • Project Value: About £8 billion at final investment decision (industry reporting); later coverage cites £8.5 billion
  • Revenue Support: Contract for difference at £37.35 per MWh in 2012 prices, for up to 15 years from commissioning
  • Construction Status: Both offshore converter stations installed; monopile installation under way since May 2026; inter-array cable installation due to begin in October 2026
  • Target Completion: Around the end of 2027 (Ørsted)
  • Jobs: Up to 5,000 during construction and up to 1,200 permanent (Ørsted)
  • Homes Powered: More than 3.3 million UK homes (Ørsted)

Project Team

Owners and Developer

Cable Installation and Supply

  • Inter-Array Cable Transport and Installation: Seaway7
  • Inter-Array Cable Supply: Hellenic Cables
  • Inter-Array Cable Supply: Prysmian Group
  • Array Cable Testing and Termination: JDR Cable Systems
  • Export Cable Supply: NKT
  • Cable Burial: Helix Robotics Solutions (official website not verified, left unlinked)

Turbines, Foundations and Vessels

HVDC Transmission

Related Project, ELMED Interconnector

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.