UK Small Modular reactors could attract £35 billion in construction investment under a proposed programme targeting 14 nuclear reactors across three sites. The initiative, advanced by SGE SMR UK, aims to establish a standardised nuclear generation fleet. Furthermore, the proposal could create substantial opportunities for British engineering, manufacturing and construction companies. More than 200 British businesses recently attended an industry briefing in Birmingham. The November 24 meeting explored potential supply chain participation in the proposed development. However, the programme remains subject to regulatory assessment and government consideration.
The proposed development would deploy GE Vernova Hitachi Nuclear Energy‘s BWRX-300 small modular reactor technology. Its planned capacity reaches approximately 4.2GW across the three proposed locations. According to SGE SMR UK, this output could represent approximately 11% of current UK electricity consumption. Additionally, the generation capacity could supply electricity to approximately eight million homes. The developer targets first power generation in 2034. It also anticipates operational lifespans ranging between 60 and 80 years.
UK Small Modular Reactors Programme Opens Construction Supply Chain Opportunities
The Birmingham briefing brought together SGE SMR UK, GE Vernova Hitachi Nuclear Energy and Samsung C&T. Together, the organisations outlined potential opportunities for domestic suppliers. These opportunities cover engineering, manufacturing, construction, electrical systems, logistics and long-term maintenance.
Consequently, British contractors could participate in several stages of the proposed nuclear construction programme. The organisers also encouraged interested suppliers to register their capabilities. This engagement will help identify companies capable of supporting large-scale reactor deployment.
Moreover, the proposed delivery model relies on standardisation and repetition. Rather than treating individual reactors as separate developments, SGE SMR UK intends to establish a coordinated fleet programme. This approach would reuse reactor designs, construction methods and delivery arrangements across successive installations.
Therefore, standardised engineering could improve construction efficiency and reduce delivery complexities. It could also support more predictable procurement and project scheduling. However, the programme must establish its final commercial and regulatory arrangements before construction commitments emerge.
SGE SMR UK chief executive Rafał Kasprów said British industry would play a critical role in fleet delivery. He highlighted the country’s established industrial capabilities and nuclear engineering heritage. Furthermore, he emphasised the importance of developing a strong domestic supply chain.
GE Vernova Hitachi Nuclear Energy will contribute its BWRX-300 reactor technology. Meanwhile, Samsung C&T brings experience in major nuclear construction projects. Its experience includes involvement in the Barakah Nuclear Energy Plant in the United Arab Emirates.
Samsung C&T senior vice president Jung Kim highlighted the importance of early supplier engagement. He also emphasised disciplined project execution and repeatable construction methods. The partnership intends to explore delivery arrangements that maximise domestic industrial participation.
UK Small Modular Reactors Face Regulatory and Delivery Milestones
Despite the industry engagement, the £35bn proposal has not secured construction approval. Instead, authorities are considering it under the Government’s Advanced Nuclear Framework. The proposal has progressed to preliminary regulatory assessment.
This stage represents an important milestone towards determining the project’s development prospects. Nevertheless, further regulatory scrutiny and approvals remain necessary before construction can proceed. The three proposed development sites also remain unnamed.
The BWRX-300 is a boiling water reactor with an individual generating capacity of 300MW. Its modular design supports factory-based manufacturing and subsequent site installation. Importantly, the technology already has a construction reference in Canada.
Ontario Power Generation is developing the first BWRX-300 unit at its Darlington nuclear site. This development provides an international reference for the proposed British deployment. However, the UK programme must still satisfy its own licensing and planning requirements.
Meanwhile, SGE SMR UK plans to establish a British office with locally recruited personnel by December 2026. The company also intends to finalise its supply chain and delivery strategy in 2027. These preparations could provide greater clarity on procurement opportunities and implementation arrangements.
If approved, the programme would represent a significant addition to Britain’s nuclear infrastructure pipeline. Nevertheless, its eventual investment requirements, construction schedule and domestic supply chain contribution remain subject to further development.

The proposed programme adds to Britain’s expanding nuclear construction pipeline, which also includes the planned prototype fusion power station at West Burton in Nottinghamshire. The UK Atomic Energy Authority’s STEP project targets the development of fusion technology for future electricity generation. These developments highlight Britain’s broader ambitions to diversify its nuclear energy infrastructure through different reactor technologies.