2000+ Acre Canoe Creek Road Data Center in Florida Sparks Fierce Opposition from Residents

Home » Buildings » Data Center » 2000+ Acre Canoe Creek Road Data Center in Florida Sparks Fierce Opposition from Residents
Canoe Creek Road Data Center

The 2,200-acre Canoe Creek Road data center project is a serious topic for discussion as developers seek to expand massively in rural areas. The massive site is prominently located in Osceola County and has been heavily marketed by real estate giant CBRE.

As a result, the local population is concerned that this aggressive hyperscale development will permanently remove the rich agricultural heritage of the region. In particular, conservationists are concerned about the destruction of valuable local wildlife habitats and sensitive water reserves. The property is currently listed for sale with a large amount of water resources already identified and permitted for industrial use.

Duke Energy will eventually provide the necessary large electrical loads, with plans to energize them by early 2028. But residents say the rapid development of clean pastures into tech centers poses a risk to their way of life. Another data center that is facing fierce opposition is the $18bn Grayslake data center in Chicago suburbs. In particular, T5 Data Centers will construct the second largest data center in Illinois. This is a huge technological campus that will eventually be used by high-powered generative AI companies in the region. But a local opposition group recently filed a lawsuit against the village to halt construction altogether.

Outlook on the Canoe Creek Road Data Center

Lifelong county resident Angelo Chiarelli documents the alarming rate of disappearing natural landscapes locally. He says that in a few weeks, dense forests and open pastures are regularly being destroyed. As a result, his conservation photography is designed to provide a strong voice for local, displaced wildlife populations. Likewise, small business owners such as Aaron Mick are very uncertain about the wider effects of the huge development. Mick Farms used to be a quiet rural area, but the encroaching housing developments caused a significant increase in daily traffic congestion. New neighborhoods might increase his farm’s clientele, but industrial pollution and water depletion are huge issues. In the end, residents want infrastructure to keep up with the region’s rapid commercial growth.

Legislative Safeguards and Utility Regulation

In response to these very issues, new Florida law safeguards everyday citizens against high industrial utility bills. Senate Bill 484 maintains local governments’ tight control over large-scale land development and hyperscale projects. In addition, Senator Carlos Guillermo Smith pointed out that utility companies have no legal authority to impose costs on families for data centers.

Duke Energy stated that it has a strong legal commitment to provide service to economic development projects approved by the local community. Fortunately, the utility recently asked for a public rate cut, which will provide some relief for residential customers by 2027. However, Smith encourages concerned residents to press hard on their local county commissioners about the proposed megaproject. In the end, Osceola County has the final say on whether or not this huge technological project is approved.

Canoe Creek Road Data Center
The 2,200-acre Canoe Creek Road data center project is a serious topic for discussion as developers seek to expand massively in rural areas

Project Overview

  • Project Value: Undisclosed
  • Location: 5300 North Canoe Creek Road, Kenansville, Florida
  • Developer: Advertised by CBRE; Power via Duke Energy
  • Status: Advertised for lease and development

Scope

  • Massive hyperscale data center campus
  • Spans more than 2,200 acres of rural agricultural land
  • Requires significant, pre-permitted regional water resources
  • Targets full electrical energization by early 2028

Project Highlights

  • Marketed directly toward massive tech hyperscalers
  • Retains pre-permitted access to critical local water reserves
  • Florida SB 484 prevents costs from shifting to taxpayers
  • Duke Energy is legally obligated to serve approved projects

Key Developments

  • CBRE aggressively marketing the sprawling Canoe Creek site
  • Duke Energy requested a public residential rate decrease recently
  • Florida passed strict laws protecting ratepayers from data center costs
  • Residents actively organizing local opposition campaigns against the build

Key Challenges

  • Protecting vulnerable local wildlife habitats and agricultural farmland
  • Managing intense community fears over severe water depletion
  • Balancing rapid technological expansion with lagging regional infrastructure
  • Preventing localized traffic congestion from worsening further

Outlook

  • Osceola County holds final authority over project approval
  • Duke Energy targets early 2028 for full site energization
  • Residents will fiercely lobby commissioners against the development
  • Hyperscale tech expansion continues encroaching on Florida farmland

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.