The Amunet II wind farm has moved from plan to build. UAE developer AMEA Power signed contracts on November 18 for the $650 million, 500 MW project at Ras Shukeir on Egypt’s Red Sea coast. Egypt’s prime minister, Mostafa Madbouly, witnessed the signing.
What the Amunet II wind farm will deliver
The project is a 500 MW wind farm that AMEA Power will own and operate as an independent power producer. It will use 45 Ming Yang turbines of 11 MW each. Once running, the farm should generate more than 2.3 billion kilowatt-hours a year, according to PowerChina. That is enough to power over 500,000 households.
The cost works out to about $1.3 million per megawatt. Meanwhile, the project grows AMEA Power’s wind capacity in Egypt to 1 GW, because it already runs the 500 MW Amunet wind farm at Ras Ghareb. That earlier farm, commissioned in June 2025, was described as the largest wind farm in Africa at the time.
Who is building it, and what else was signed?
The build is split between two Chinese groups. AMEA Power signed an engineering, procurement, and construction (EPC) contract with PowerChina International and PowerChina Huadong Engineering Corporation (HDEC). A separate turbine supply agreement links Ming Yang and HDEC.
PowerChina says Ras Shukeir is its fourth wind project in Egypt under an EPC model. As a result, it says its contracted wind capacity in the country has reached 2.3 GW, which it calls the largest of any wind EPC contractor in Egypt. The signing went beyond one wind farm. AMEA Power and Ming Yang also agreed to build Egypt’s first wind turbine factory in the Suez Canal Economic Zone. The factory is planned to produce 3 GW of turbines a year, both for Egyptian projects and for export to Africa, with an investment of about $200 million. In total, the three contracts are worth about $850 million, according to the Cabinet statement.

What happens next for AMEA Power in Egypt?
The company is building a large pipeline. AMEA Power’s chairman, Hussain Al Nowais, said its wind and standalone battery projects in Egypt have a combined capacity of up to 5,000 MW, with total investment of about $3 billion. Its Egyptian portfolio already includes the 500 MW Abydos solar plant and a 1 GW Abydos 2 solar plant with 600 MWh of battery storage.
The reports I found do not give a start date or a commissioning date for Amunet II. The next milestones are the mobilization of the EPC contractor, the first turbine deliveries, and the progress of the turbine factory in the Suez Canal zone. Egypt’s wind build-out is busy. For example, the 900 MW Shokeir wind farm in the Gulf of Suez reached financial close earlier this month.
Other projects
The GameChange Solar Benban project in Egypt is gaining momentum after GameChange Solar secured a 258 MWp solar tracker order for the massive Benban Solar Park. The agreement will supply advanced tracker systems that improve photovoltaic performance. Moreover, the contract, estimated at $120 million, supports Egypt’s expanding renewable energy sector. The new order will also strengthen solar power generation at one of the largest solar complexes in the world.