Project Overview
- Project Name: Xiaowan Hydropower–Solar Complex
- Project Type: Hybrid renewable energy (hydropower + solar)
- Capacity: ~5.4 GW (4.2 GW hydro + 1.23 GW solar)
- Purpose: Integrated renewable generation and grid stability
- Status: Commissioned
Key Stakeholders
- Developer / Operator: China Huaneng Group
- Operator (Subsidiary): Huaneng Lancang River Hydropower Co., Ltd.
- Country: China
Location
- Province: Yunnan
- River: Lancang River
- Site: Xiaowan Hydropower Station
Scope
- Integration of 16 solar PV plants
- Combined hydro and solar generation via single system
- Coordinated control and transmission infrastructure
Funding / Delivery Model
- State-owned enterprise development
- Domestic technology and equipment integration
- Centralized control and grid coordination system
Status
- Fully commissioned and operational
- Integrated hydro-solar system active
- Delivering combined power output
Key Risks & Challenges
- Complex hydro-solar coordination
- Stability and grid integration challenges
- High technical requirements for control systems
Strategic Significance
- Major milestone in hybrid renewable systems
- Enhances grid reliability and flexibility
- Strengthens China’s renewable energy capacity
Technical Features
- 292 m arch dam with ~15 billion m³ reservoir
- Six 700 MW turbines (hydropower)
- Millisecond response for load balancing
- Acts as large-scale natural energy storage system