Belyando Energy Project: 1.44GW Renewable Construction Plan Advances in Queensland Coal Region

Home » Belyando Energy Project: 1.44GW Renewable Construction Plan Advances in Queensland Coal Region
Belyando Energy Project

Belyando energy project is advancing through Australia’s environmental approval process, with plans for a major renewable energy development in Queensland’s coal-producing region. The proposed development will combine wind generation, utility-scale solar and battery storage near Moranbah. It will deliver approximately 940MW of renewable generation capacity alongside substantial electricity storage.

Moreover, its integrated design will place three energy technologies within one development. The proposal represents a significant infrastructure investment in Queensland’s industrial heartland, although Acen Australia has not disclosed its construction budget.

The development will occupy approximately 1,670 hectares across four land parcels. These properties currently support agricultural activities, primarily cattle grazing. Importantly, the project intends to accommodate continued grazing alongside its renewable energy infrastructure.

The developer lodged its federal environmental referral under Australia’s Environment Protection and Biodiversity Conservation (EPBC) Act on November 25, 2026. The submission initiates the federal environmental assessment process and opens the proposal to public scrutiny.

Belyando Energy Project combines three construction components

The Belyando energy project will integrate up to 440MW of wind generation with a 500MW solar farm. Additionally, its proposed battery energy storage system will provide approximately 500MW of power output and 1,600MWh of storage capacity.

The wind component will feature up to 55 turbines, each with approximately 8MW capacity. These turbines would exceed the capacity of individual wind turbines currently installed in Australia, according to Renew Economy.

Furthermore, the solar installation will contribute another 500MW of generation capacity. The battery system will store electricity and release it when demand increases or renewable generation declines.

Consequently, the combined development will provide approximately 940MW of renewable generation capacity. Its battery will independently provide 1,600MWh of storage.

Belyando Energy Project prioritises environmental considerations

The development’s location offers access to Queensland’s industrial and agricultural load centres. It also sits close to existing transmission infrastructure, potentially reducing additional network development requirements.

However, environmental considerations have already influenced the proposed construction footprint. Ecological assessments identified extensive koala and greater glider habitat within the southern section.

Consequently, ACEN removed that section from the proposed development design. This adjustment demonstrates how ecological assessments have influenced the project’s infrastructure planning.

The construction programme will require several supporting infrastructure components. These include internal access tracks, underground electrical cabling and overhead transmission lines.

Additionally, the developer plans to install up to six collector substations and an electrical switching station. The project will also require onsite maintenance infrastructure and associated electrical facilities.

Meanwhile, Queensland’s renewable energy planning framework requires environmental and community considerations during development assessment. Wind farms, large solar farms and qualifying battery facilities undergo impact assessment and public notification.

Belyando Energy Project enters federal approval process

The federal environmental assessment represents an important milestone before construction can proceed. The Department of Climate Change, Energy, the Environment and Water will consider the project’s environmental implications.

However, the federal referral does not constitute final construction approval. The proposal must also satisfy applicable Queensland planning and development requirements.

The project will join Acen Australia’s expanding renewable energy portfolio. The company owns the 400MW Stubbo Solar Farm and is developing the 720MW New England Solar Farm in New South Wales.

Furthermore, Acen reports more than 1GW of renewable energy capacity under construction and in operation. Its development pipeline exceeds 13GW across solar, wind, battery and pumped hydro projects.

The Belyando development could therefore strengthen Queensland’s electricity infrastructure through diversified generation and storage. Nevertheless, its construction schedule, final investment decision and capital expenditure remain unconfirmed.

Australia is also expanding grid-scale energy storage through projects such as the $1.05 billion Collie Battery Hub in Western Australia. The 500MW/2GWh facility will strengthen electricity supply as the country transitions away from coal-fired generation. Both developments highlight Australia’s growing investment in renewable energy infrastructure, particularly large-scale battery systems supporting intermittent wind and solar generation.

Belyando hybrid Energy Project

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.