The first phase of Thailand’s THB179.4 billion (US$5.47 billion) Thai-Chinese High-Speed Rail project is running far behind schedule. The 250.77-kilometre line links Bangkok’s Krung Thep Aphiwat Central Terminal with Nakhon Ratchasima. Cumulative construction progress stands at just 52.4 per cent. That is 28.2 percentage points short of the programme’s own target of 80.73 per cent at this stage.
Anan Phonimdaeng, deputy governor and acting governor of the State Railway of Thailand (SRT), shared the figures on 23 March 2026. He admitted that the 2030 opening target is now “very tight.” That date was already a revision of earlier plans. Civil works still need at least three and a half more years. Only then can system installation under Contract 2.3 begin. Two of the 14 civil works contracts have not started yet. Meeting 2030 now depends on solving several separate crises at once. These range from a fatal crane accident to pending government approvals.
A Project of 14 Contracts: Where Each Section Stands
The Bangkok–Nakhon Ratchasima phase consists of 14 civil works contracts. Each one covers a different section of the route. The 250-kilometre corridor crosses flat central plains, elevated urban approaches, mountain tunnels and dense city areas. The number of contracts reflects this varied terrain. It also reflects the fragmented way the project has bought its works. So far, two contracts are complete. The Department of Highways finished Contract 1-1, the 3.5-kilometre Klang Dong–Pang Asok transition section, for THB362 million. Civil Construction Services & Products Company Limited delivered Contract 2-1, the 11-kilometre Sikhio–Kut Chik section, for THB3.11 billion.

Two Sections Near the Finish Line
Ten contracts are now under construction, and their progress varies widely. Two are close to done. Contract 3-2 covers the Muak Lek and Lam Takhong tunnels (12.23 km, THB4.28 billion). Nawarat Patanakarn PCL has finished 99.8 per cent of the work. Contract 3-4 has also reached 99.8 per cent. This 37.45-km, THB9.85 billion section runs from Lam Takhong to Sikhio and from Kut Chik to Khok Kruat. Italian-Thai Development PCL is the contractor.
However, work on Contract 3-4 has stopped after a fatal accident. A construction crane fell onto a Special Express Diesel Railcar train on the Krung Thep Aphiwat–Ubon Ratchathani route. The accident killed up to 32 people. Work cannot restart until the Office of the Attorney General finishes its investigation. The outcome could lead to the contract’s termination. That would be a serious setback for a section that is almost finished.
At the other extreme sits Contract 3-5, the 12.38-km Khok Kruat–Nakhon Ratchasima section worth THB7.75 billion. The SPTK JV, made up of Napa Construction, Tim Sekata and Bina Puri, holds this contract. It is only 17.6 per cent complete, an 81.9 per cent delay against its target. No other contract on the route lags this badly.
The delay stems from a late design change in the Korat urban area. Planners swapped an embankment for an elevated track, which raised the budget. Now the new Cabinet must approve the revised cost before work can move forward. Two other contracts held by Unique Engineering and Construction PCL are also far behind. Contract 4-2 (Don Mueang–Navanakorn, 21.80 km, THB10.57 billion) is 10.1 per cent complete. That leaves it 58.9 per cent behind schedule. Meanwhile, Contract 4-6 (Phra Kaeo–Saraburi, 31.60 km, THB9.43 billion) has reached 20.7 per cent. It is running 46.5 per cent late.
The Two Unstarted Contracts
Two contracts have not yet entered construction. These are Contract 4-1 (Bang Sue–Don Mueang) and Contract 4-5 (Ban Pho–Phra Kaeo, including Ayutthaya station). Both are among the most politically and legally complex sections of the route.
Contract 4-1: Overlap with the Airport Rail Link. The northern end of Contract 4-1 overlaps with a separate high-speed rail link. That link will connect Bangkok’s three airports: Suvarnabhumi, Don Mueang and U-Tapao. There is still no agreement on how to build, own and fund the shared infrastructure in this corridor. SRT has sent a revised draft contract to the Office of the Attorney General and is waiting for a response. The draft aims to align the structures of the two programmes. The incoming government must also approve it.
Contract 4-5 faces a different challenge. Its original design included a full-scale station at Ayutthaya, a UNESCO World Heritage Site. A Heritage Impact Assessment is now complete. Its findings mean the station’s footprint must shrink to meet UNESCO rules and Thai heritage law. SRT must redesign the station within the same contract framework. It must then re-tender the work to a new contractor. SRT expects to finish the new design within six months and send it to the SRT board. A tender launch will follow. If all goes to plan, track structure work on this section could start before the end of 2026. On top of these problems, SRT has no functioning board and no permanent governor. Many decisions must wait until a new board and chairman are in place. These include contract extensions, budget revisions and the formal employment contract for the SRT governor. This gap in leadership has nothing to do with the construction problems themselves. Yet it directly limits the project’s ability to respond to them.
Contract 2.3: The System That Cannot Begin Until Civil Works Finish
The biggest sequencing challenge for Phase 1 lies in its link to Contract 2.3. SRT signed this agreement in 2019 with a Chinese consortium led by CRRC. It covers rail, electrical and mechanical systems, rolling stock and staff training. In short, it includes everything that follows the civil works. That means track laying, overhead lines, signaling and communications, traction power and the EMU trainsets that will run the route. The contract’s five-year term expires in 2026. Yet SRT still cannot issue a Notice to Proceed. The civil works teams have not handed over enough continuous sections of the route.
SRT is discussing a solution with the Chinese side. Under this plan, systems work would start on each finished section as soon as civil teams hand it over. CREC and the systems partners would not need to wait for all civil works to end. Running both tasks in parallel could shorten the overall schedule. However, the Chinese contractors must first agree on contract terms, a revised work plan, and costs. Anan has confirmed that SRT will negotiate a new contract extension with its Chinese partners. This will form part of a wider programme reset. The talks will take time. They will also add another layer of bilateral complexity. The project already demands constant coordination between two governments. That work spans many ministries, state enterprises and contractors.
Thailand’s Rail Ambitions and the Wider Southeast Asian HSR Landscape
The Bangkok–Nakhon Ratchasima phase is the first installment of a much larger vision: a continuous high-speed rail connection from Bangkok through Nakhon Ratchasima to Nong Khai on the Mekong River, where the line would cross into Laos and connect with the Laos–China Railway opened in December 2021—creating an unbroken standard-gauge link from Singapore to Kunming and, ultimately, to the Chinese high-speed rail network. Phase 2, from Nakhon Ratchasima to Nong Khai, was approved by the Thai Cabinet at a projected cost of US$10 billion covering 357 kilometres, with a construction timeline targeting completion by 2030 and operations beginning by the end of 2031—including five new stations and a Na Tha transshipment center at Nong Khai to handle gauge changes between the standard-gauge high-speed line and the 1-meter-gauge network. Phase 1’s delays therefore have cascading implications: a 2030 or later opening of Bangkok–Nakhon Ratchasima pushes the Phase 2 program back correspondingly, delaying the full realization of Thailand’s strategic connectivity ambitions and the broader Belt and Road-aligned infrastructure logic of the Pan-Asia Railway Network.
Thailand is not alone in wrestling with the realities of delivering Chinese-technology high-speed rail on complex greenfield alignments. Indonesia’s Jakarta–Bandung High-Speed Railway, opened in October 2023 after years of cost and schedule overruns under a consortium including CRRC and Wijaya Karya, provided a regional reference point for both the achievability and the difficulty of the model. The Laos–China Railway—built largely on more straightforward terrain with significantly higher Chinese state direction over procurement and execution—opened on time in 2021, but operates at lower speeds than a true HSR service. Thailand’s Phase 1, at THB179.4 billion and 250 kilometres through varied terrain including urban Bangkok approaches, mountainous tunnels, and newly elevated urban sections, represents a more complex undertaking — and the 28-point programme gap exposed in March 2026 is the clearest signal yet that closing it within four years will require solutions that go beyond the construction site and into the highest levels of both governments.
Other projects
The two partners already work together in Chonburi. In January, Amata B.Grimm Power signed a 100 MW power purchase agreement with NTT GDC for its Bangkok 4 data center. B.Grimm called it the largest power deal in its history, and commercial operation is scheduled for June 2027. NTT has also broken ground on the Bangkok 4 campus, and it already operates Bangkok 2 and Bangkok 3 in the same area. B.Grimm has its own data center plans too. It is building a 96 MW hyperscale facility in Chonburi, and it aims for 300 MW of data center capacity by 2030. As a result, the new 400 MW study would be larger than the group’s earlier targets.





Leave a Reply