Agratas Somerset Gigafactory Factsheet
Client and OwnerAgratas (Tata Group’s global battery business)
Anchor CustomerJaguar Land Rover (JLR)
LocationGravity Smart Campus, near Bridgwater, Somerset
Estimated Value£4bn–£5.2bn total investment (backed by £380m in UK government subsidies)
Scale and Output244,710 sq m for Building One and ancillary structures; 40GWh total planned capacity (supplying nearly half of the UK’s projected automotive battery demand by the early 2030s)
Economic ImpactExpected to create 4,000 direct jobs and contribute £700m annually to the local economy
Key Delivery Partners:
- Lead Design: Stantec
- Planning: Turner & Townsend
- Steelwork: Severfield (frame completed January 2026)
- M&E Services: NG Bailey (stepped in after TClarke exited in March 2026)
- Main Contractors: Sir Robert McAlpine (appointed July 2024; exited June 2026), succeeded by Tonroe Group Ltd / TSL (summer 2026–present)
TimelineInitially targeted for 2026 production, pushed back to 2027/early 2028 following redesigns and contractor transitions.