Alabama’s $3.2B Mobile River Bridge Advances with Tower Foundation Work

Home » Transport » Bridges » Alabama’s $3.2B Mobile River Bridge Advances with Tower Foundation Work
Alabama's $3.2B Mobile River Bridge project advances with tower foundations and approach construction, targeting completion in October 2031.

Factsheet: I-10 Mobile River Bridge and Bayway Project

  • Project: I-10 Mobile River Bridge and Bayway Project
  • Location: Mobile and Baldwin counties, Alabama, USA
  • Project owner: Alabama Toll Road, Bridge and Tunnel Authority
  • Project agency: Alabama Department of Transportation (ALDOT)
  • Phase One construction value: $3.2 billion
  • Bridge type: Six-lane cable-stayed bridge
  • Main crossing: Mobile River
  • Construction contractor: Kiewit Massman Traylor joint venture
  • Delivery method: Design-build
  • Tower foundation work: Began October 2026
  • East approach bridge: Construction began November 2026
  • West approach bridge: Scheduled to begin January 2027
  • Existing Bayway improvements: Approximately one mile of reconstruction and restriping of the 7.5-mile facility to three lanes in each direction
  • Major financing: $2.52 billion TIFIA loan, bond financing, federal grants and state investment
  • Expected completion: October 2031
  • Future development: Phase Two includes construction of a new Bayway structure, subject to additional funding

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *