Construction of Alabama’s $3.2 billion I-10 Mobile River Bridge and Bayway Project is progressing through its early structural development phase, with foundation work underway for the new bridge towers and construction beginning on the eastern approach structure. The Alabama Department of Transportation (ALDOT) has outlined additional milestones through January 2027, as the project advances toward delivering a new six-lane cable-stayed crossing over the Mobile River.
The latest construction update, issued November 25, 2026, provides a closer look at how the principal bridge structure and its connecting roadway infrastructure are taking shape. The current activities mark an important transition from preliminary construction preparations into the development of the foundations and approach structures needed to support the new interstate crossing.
Tower foundations and approach bridges establish the main crossing
Foundation work for the east and west towers of the Mobile River Bridge began in October 2026. These foundations will support the two principal towers, or pylons, of the cable-stayed structure, which will carry the bridge’s main span across the Mobile River.
The next milestone arrived in November, when construction began on the east approach bridge. This structure will connect the new cable-stayed crossing to the existing Bayway on the eastern side of the river, providing the roadway transition between the main bridge and the existing highway infrastructure.
Work on the west approach bridge is scheduled to begin in January 2027. It will connect the new crossing to the existing I-10 corridor on the western side of the Mobile River.
Together, these structures will establish the principal connections needed to integrate the new bridge into the interstate network. Following the foundation and approach work, construction will progress through the erection of the east and west towers, development of the main-span superstructure and installation of the stay cables.
ALDOT has indicated that more detailed schedules for these subsequent construction activities will be released as the project advances. The department also cautions that construction timelines may change depending on weather, site conditions and other factors.
$3.2 billion Phase One includes wider Bayway and interstate improvements
The Mobile River Bridge forms part of a broader $3.2 billion Phase One construction programme. In addition to the new six-lane cable-stayed bridge, the programme covers the reconstruction of approximately one mile of the existing Bayway and the restriping of the entire 7.5-mile facility to provide three lanes in each direction.
The project will also upgrade major interchanges and intersections and improve traffic operations along the I-10 corridor in Mobile and Baldwin counties. These upgrades aim to increase interstate capacity, improve regional mobility and strengthen connections across the Gulf Coast’s freight and commercial networks.
The Alabama Toll Road, Bridge and Tunnel Authority secured financing for Phase One in September 2026. The funding package includes a $2.52 billion Transportation Infrastructure Finance and Innovation Act (TIFIA) loan from the U.S. Department of Transportation’s Build America Bureau, as well as bond financing, federal grants and state investment.
The Kiewit Massman Traylor joint venture is delivering the programme through a design-build contract. The project moved into full construction following the September 2026 financing close and construction authorization.
Longstanding limitation of the existing interstate route
The new bridge will address a longstanding limitation of the interstate route. Because hazardous-material freight vehicles cannot use the Wallace Tunnel, they must travel through local streets and surrounding communities. The new crossing will give these vehicles a direct interstate route while helping reduce congestion along I-10.
The Mobile River Bridge’s development is part of a wider wave of investment in major highway crossings across the United States. In New York and New Jersey, the Port Authority is pursuing a different infrastructure strategy after an engineering study found that widening the aging Outerbridge Crossing could be considerably more expensive and time-consuming than constructing a replacement. The contrast between the two projects highlights the different engineering and investment decisions involved in maintaining existing crossings and delivering new bridge infrastructure.
ALDOT anticipates that the Mobile River Bridge and Phase One improvements will be completed in October 2031. A subsequent Phase Two is planned to include construction of a new Bayway structure as additional funding becomes available, extending the project’s long-term transformation of the I-10 corridor.