Amtrak has scrapped its $900 million Bridgeport rail yard plan, clouding the White Sox stadium vision near the South Loop. The railroad announced Tuesday that it will redevelop its existing 14th Street yard instead of moving maintenance operations to Bridgeport. In addition, Amtrak will no longer be selling the 14th Street property. That land is at the heart of developer Justin Ishbia’s stadium megadevelopment.
The ruling is a hard blow for the Railyards concept. Ishbia is a White Sox owner and waits for the team’s biggest opportunity. In addition, his Railyards idea revitalized Amtrak’s 14th Street site with a new stadium. In addition, Block Club Chicago says the announcement’s impact on those plans is still unknown. In the meantime, Amtrak’s turnaround was not about real estate, but about operations. “The firm will prioritize critical infrastructure needs, better support for new trains and support the advancement of future growth in service in the Midwest,” said spokesman Marc Magliari in a statement.
Other Projects
In other rail projects, the Columbia River Bridge Replacement is in the request-for-proposals phase in Washington. On Nov. 23, WSDOT released the final RFP, fillable forms and Schedule B progressive design-build contract documents. In addition, the five-mile Interstate Bridge Replacement corridor is estimated to cost $13.5 billion to $15.2 billion. The estimated amount is around $14.4 billion. Meanwhile, the bridge contract itself holds an estimated value of $3.3 billion to $3.885 billion.
Scope of the White Sox stadium plan fallout
The cancelled plan cost approximately $900 million. It would have transferred Amtrak’s maintenance to the existing Canal Street rail yard in Bridgeport. Moreover, that plan was met with strong opposition from nearby residents who objected to the industrial siting in their community. The reversal thus gives those opponents a clear victory.
Ald. Nicole Lee of the 11th Ward was happy about the change. The Bridgeport site, which was “squarely in the middle of a residential area,” was not a viable site for this maintenance facility, Lee said. In addition, she presented the result as a community triumph. We have been fighting hard to make sure that this project didn’t ruin the neighborhood that thousands of Chicagoans call home, and we are proud that we did not,” Lee said.
The federal machine has already been realigned. Amtrak is making a change, according to Magliari, and is going in a different direction, with the US Department of Transportation’s approval. Moreover, the Federal Railroad Administration has agreed to rescope its grant to reflect the new approach. Meanwhile, Amtrak had planned a series of public feedback meetings on the Bridgeport project for early December. The turnaround came first, as the railroad switched to its existing South Loop yard.
Outlook for the Bridgeport Rail Yard Plan Development
The stadium path is now blocked with a hard block. The Canal Edge company owned by Ishbia had been looking to build on the 14th Street site for the Railyards megadevelopment. But Amtrak no longer wants to sell that land. So, a change in policy or a new site would be required for the development to go ahead. But Lee indicated that the discussion is ongoing.
The alderwoman also referenced upcoming discussions regarding “the future of the White Sox. In addition, she supported “a path to reimagining 35th Street to be a more vibrant economic environment surrounding our team. That work must begin today. In addition, Canal Edge and the private equity firm behind Ishbia, Shore Capital Partners, did not respond before publication. In the end, there are two timelines. The firm moves forward with revamped 14th Street redevelopment. In the meantime, the stadium issue awaits Ishbia’s reply and the next steps of the city.