The Columbia River Bridge Replacement is in the request-for-proposals phase in Washington. On Nov. 23, WSDOT released the final RFP, fillable forms and Schedule B progressive design-build contract documents. In addition, the five-mile Interstate Bridge Replacement corridor is estimated to cost $13.5 billion to $15.2 billion. The estimated amount is around $14.4 billion. Meanwhile, the bridge contract itself holds an estimated value of $3.3 billion to $3.885 billion.
The project is replacing the current Interstate 5 bridges between Vancouver, Washington and Portland, Oregon. In addition, WSDOT oversees the primary contract in conjunction with the Oregon Department of Transportation. The delivery is based on a progressive design-build approach, where the owner, designer and contractor are engaged early in the design process. This means that WSDOT can negotiate costs as designs evolve, instead of committing to a price up front.
Other Projects
Amtrak has scrapped its $900 million Bridgeport rail yard plan, clouding the White Sox stadium vision near the South Loop. The railroad announced Tuesday that it will redevelop its existing 14th Street yard instead of moving maintenance operations to Bridgeport. In addition, Amtrak will no longer be selling the 14th Street property. That land is at the heart of developer Justin Ishbia’s stadium megadevelopment.
Scope of the Columbia River Bridge Replacement
The contract is for two new fixed-span bridges west of the existing Interstate 5 bridges. Three through lanes and one auxiliary lane are provided in each direction, with safety shoulders for emergency access. In addition, the southbound bridge has a deck for future light rail service in both directions. Track installation is a separate contract, however. In the meantime, the northbound bridge provides a shared-use path for pedestrians and cyclists. It connects the North Portland Harbor bridge, Hayden Island streets, the new crossing and Vancouver’s waterfront.
Highway work is shared between both states. In addition, the developer will rebuild the Hayden Island Interchange and reconnect to N. Tomahawk Island Drive, N. Hayden Island Drive and N. Parker Avenue. On the Washington side, the scope enhances the I-5 and SR 14 connections, such as ramps to downtown Vancouver. Other works include traffic detours, utility coordination, stormwater facilities and construction staging. Lastly, the contract calls for the demolition of both the old bridge structures after replacement, in conjunction with the construction programme.
Outlook for the $14 billion corridor programme
The procurement calendar is now fixed. The deadline for proposals is March 24, 2027. In addition, interviews are April 12-16 and WSDOT designates the top-scoring proposer May 26. As a result, the contract execution will take place on July 30, 2027, with the start of Phase 1 design services. After that, initial Phase 2 authorization comes in October 2, 2028, and construction is scheduled to be completed in the fourth quarter of 2036.
There is one team left in the field. The qualification round ended Sept. The project was awarded to Columbia River Constructors, a JV of Kiewit, Guy F. Atkinson and Traylor Bros. with a single Statement of Qualifications. In addition, WSDOT determined the submission was responsive and advanced the team on Nov. 12. Therefore, open-book pricing and an independent cost-estimation process will be used to determine if proposed costs are reasonable.
There is a lot of money in the stack. The first funded construction phase has about $5.69 billion in it, including tolling infrastructure, highway connections, demolition and light rail advancement. Furthermore, there is a $600 million federal MEGA grant in committed money. A $1.5 billion Bridge Investment Program grant is another feather in its cap. The stack then includes $650 million in formula funding, $350 million from Washington and $1 billion from Oregon HB 5005. Lastly, $90 million in previous state money is added to $1.5 billion in estimated toll revenue. However, the programme aims to raise approximately $1 billion via the FTA’s Capital Investment Grant program.