Applied Digital Polaris Forge 2: 25 MW Ready, $5B Lease

Home » Buildings » Data Center » Applied Digital Polaris Forge 2: 25 MW Ready, $5B Lease
Applied Digital Polaris Forge

Applied Digital Polaris Forge 2 has delivered its first capacity. On November 24, the company said it completed base-build commissioning of the first 75 MW of a 150 MW data center building in Harwood, North Dakota. It also finished the fit-out of the first 25 MW data hall and reached “ready for service” on schedule.

What the Applied Digital Polaris Forge milestone covers

The company builds each 150 MW building in two 75 MW phases. Each phase includes three 25 MW data halls, and crews test the three halls together. The first phase is now commissioned, and one hall is fitted out and ready.

The remaining 50 MW of this phase will move through fit-out and delivery to the customer. In addition, a second 75 MW phase follows to complete the building. This is the first ready-for-service milestone at Polaris Forge 2. It follows 250 MW of operating critical IT load at the company’s first campus, Polaris Forge 1 in Ellendale, North Dakota.

Who the capacity serves

The whole building is fully leased. It forms part of a 200 MW long-term lease with an unnamed hyperscale customer. When the company announced that lease in October 2025, it described about $5 billion in contracted revenue over roughly 15 years. That figure is expected rent, not construction cost. Applied Digital now reports more than $41 billion in contracted base-term lease revenue across its portfolio.

How big the campus could become

Capacity figures differ by source. The company’s August 2025 plan described a $3 billion, 280 MW campus. A supplier release later described 300 MW across two 150 MW buildings, and one industry report says the campus could eventually reach 1 GW. Therefore, the final size depends on future phases and customers.

Applied Digital Polaris Forge
Polaris Forge 2 is the company’s second AI data center campus in North Dakota

What happens next?

The next steps are fitting out the other two halls in the first phase, then commissioning the second 75 MW phase. Delivery on schedule matters because hyperscale customers pay once capacity is ready.

Other data center builds are moving in the Plains and Texas as well. For example, Giga Energy signed a $1 billion, 10-year lease for a 60 MW data center in Hunt County, Texas.

Other projects

Basin Electric has selected PCL Industrial as general contractor for North Dakota’s largest power plant, the Bison Generation Station. The plant is a new $4 billion natural gas-fired power plant in Williams County, North Dakota. The scope of the project represents one of the largest investments ever undertaken by Basin Electric. Furthermore, it advances Basin’s ambition to provide reliable, dispatchable power to meet growing traditional-load demands.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *