XTX Markets Opens First Data Center in Finland as €1Billion Kajaani Campus Faces Power Permit Delays

Home » Buildings » Data Center » XTX Markets Opens First Data Center in Finland as €1Billion Kajaani Campus Faces Power Permit Delays
XTX Markets Opens First Finnish Data Center as €1 Billion Kajaani Campus Faces Power Permit Delays

British quantitative trading firm XTX Markets has completed its first data center in Kajaani, Finland, marking a major milestone in its plans to establish a €1 billion-plus high-performance computing campus in the country. However, the company has warned that delays in securing permits for electricity transmission infrastructure could slow the delivery of additional facilities.

The newly completed facility is the first of five data centers planned along the Kajaani River. XTX Markets began construction in 2024. The first building provides approximately 15,000 square meters of space and 22.5MW of IT capacity. The facility also represents the first move by billionaire Alexander Gerko’s company into owning and operating its own large-scale data center campus.

The investment is driven by XTX Markets’ growing demand for computing resources to support its machine-learning models and algorithmic trading operations. The company uses artificial intelligence (AI) to analyze financial markets and generate price forecasts across thousands of financial instruments. These require substantial high-performance computing capacity.

According to XTX Markets, its computing requirements have grown beyond what it can efficiently secure through third-party infrastructure providers, prompting the decision to develop dedicated facilities.

Construction of XTX Markets Data Center in Finland

XTX Markets’ €1 Billion Data Center Campus in Kajaani, Finland

The completed facility is only the first phase of a considerably larger development. XTX Markets announced plans in January 2025 to invest more than €1 billion in a five-building data center campus on a 478-acre site in Kajaani.

The wider campus is expected to include five data centers. These will also be supported by associated mechanical infrastructure, warehouse facilities and office accommodation. The first building alone includes three data halls, with a combined IT capacity of 22.5MW. It also has a mechanical plant area, warehouse and office space designed to accommodate approximately 50 people.

XTX Markets has already invested more than €400 million in construction in Kajaani, according to its chief operating officer, Mike Irwin. The majority of this expenditure has gone to contracts with Finnish companies, reinforcing the project’s role in supporting the country’s domestic construction and engineering sectors.

Second XTX Markets data center in Kajaani expects 2027 completion

The second data center is expected to be completed in 2027. Meanwhile, construction of the third facility is progressing through successive contract packages. Finnish contractor YIT has also been engaged to deliver its shell and core works, followed by interior finishing, mechanical and electrical (MEP) installations and commissioning.

In September 2026, YIT announced a further agreement with XTX Markets covering the third facility’s interior finishing and building services engineering. The latest contract phase is scheduled to begin towards the end of 2026, although its financial value has not been disclosed.

The five-building development is currently progressing beyond its initial construction phase, with multiple facilities at different stages of delivery. Nevertheless, the long-term €1 billion expansion program remains dependent on the availability of sufficient electricity and the infrastructure required to connect the campus to Finland’s power grid.

Electricity Infrastructure and Permit Delays Threaten Expansion Timeline of XTX Markets Data Center in Finland

Despite completing its first data center facility, XTX Markets has raised concerns about the pace of electricity infrastructure development in Finland.

The company says electricity supply and grid connections have been secured for its first two data centers. However, the availability of power for subsequent facilities remains uncertain. This has the potential to affect the pace at which the wider campus can be delivered.

A particular concern is the processing of permits associated with acquiring land for electricity transmission lines. XTX Markets’ COO Mike Irwin has criticized the lengthy approval process for permits allowing land to be expropriated for power-line construction. Irwin argues that administrative delays are making it difficult to advance the company’s investment program.

CPU and GPU racks inside XTX Markets Data Center in Finland

The issue highlights an important challenge facing large-scale data center construction in Finland and other European markets. Securing a site and completing the buildings does not necessarily guarantee that sufficient electricity will be available when additional computing capacity is required. Other projects in the country may also face this reality, including the $1 billion Tiktok Data Center Campus in Finland. The facility is also planned as the company’s second in Europe.

For XTX Markets, the problem is particularly significant. This is because its expansion strategy involves developing its own computing infrastructure ahead of anticipated demand. Delays in power transmission projects could therefore create a mismatch between the completion of new data center buildings and their ability to operate at the intended capacity.

The company’s concerns also place greater attention on the supporting infrastructure required to deliver Finland’s growing data center pipeline. This includes substations, high-voltage transmission connections and associated land acquisition and permitting processes.

Kajaani Investment Brings Local Construction and Employment Opportunities

Beyond its computing infrastructure, the XTX Markets development is expected to generate wider economic benefits for Kajaani and the surrounding Kainuu region.

XTX Markets has employed Finnish contractors for much of the construction work. This includes YIT, which is responsible for major building packages. More than 30 full-time employees, including engineers and personnel responsible for security and maintenance, are already based at the Kajaani site. Further recruitment is expected.

The project also incorporates sustainability considerations suited to its northern Finnish location. XTX Markets intends to use the area’s naturally low temperatures to support cooling operations. This will help reduce the need for water-intensive cooling systems. The company has also explored opportunities to recover waste heat generated by the data centers and make it available to the local community.

On November 24, 2026, Kajaani announced that XTX Markets had committed €1.6 million to local initiatives. These also include community participation, recreational services and education and skills development related to the data center sector. The contribution adds another angle to the company’s growing presence in the region.

With the company’s first data center in Finland now completed and the second expected in 2027, XTX Markets is establishing Kajaani as a significant location for its future computing requirements. However, the ultimate scale and delivery pace of the more than €1 billion campus will strongly depend on whether the electricity and grid permits can keep pace with the company’s expansion ambitions.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *