Project Fact Sheet
NameCARBON Photovoltaic Gigafactory.
TypeIntegrated photovoltaic manufacturing complex.
LocationFos-sur-Mer, Bouches-du-Rhône, Provence-Alpes-Côte d’Azur, France.
DeveloperCARBON.
InvestmentApproximately €1.5 billion (US$1.74 billion).
Site AreaApproximately 45 hectares.
Original Production Capacity5GW annually.
Planned Manufacturing OutputMore than 10 million photovoltaic panels annually.
Manufacturing ScopeSilicon processing, solar cell manufacturing and photovoltaic module assembly.
Building PermitObtained in 2025.
Environmental AuthorisationsObtained in 2025.
National Project StatusDesignated Major National Interest Project in July 2024.
Original Construction ProgrammePreparatory activities targeted for 2025.
Original Operational Target2027.
Employment TargetApproximately 3,000 direct jobs.
Actual Development ExpenditureApproximately €21 million, according to reporting by Le Monde.
Public FundraisingApproximately €2.96 million from 2,379 individual investors.
Project CancellationAnnounced May 19, 2026.
Project Company LiquidationTELI SAS entered judicial liquidation in May 2026.
Current Project StatusAbandoned; previously announced construction and commissioning schedules no longer apply.
Project Team
DeveloperCARBON.
President and Co-FounderPierre-Emmanuel Martin.
Co-Founders:
- Pascal Richard.
- Laurent Pélissier.
- Gaëtan Masson.
Industrial Technology PartnerECM Group.
Solar Manufacturing Industry PartnerACI Group.
Research and Technology PartnerISC Konstanz.
Proposed Strategic Manufacturing PartnerLONGi.
Public Investment and Fundraising PartnerEnerfip.
Former Proposed Industrial Acquisition PartnerEDF Renouvelables, through the proposed Photowatt transaction.
Government Planning AuthorityFrench Government.
Host MunicipalityFos-sur-Mer.
Port Infrastructure AuthorityGrand Port Maritime de Marseille.