Cheniere Sabine Pass Expansion: FERC Approves 20 mtpa

Home » Energy » LNG » Cheniere Sabine Pass Expansion: FERC Approves 20 mtpa
Cheniere Sabine Pass expansion

 

The Cheniere-Sabine Pass expansion has cleared its biggest regulatory hurdle. US federal regulators approved Cheniere Energy’s application to expand its Sabine Pass LNG plant in Louisiana by 20 million tonnes a year. Specifically, the Federal Energy Regulatory Commission (FERC) gave the approval on Thursday, November 19, moving the project one step closer to a final investment decision.

What FERC approved for the Cheniere Sabine Pass expansion

The approval covers a three-train expansion of the plant, with a peak capacity of about 20 million tonnes a year, including debottlenecking. In addition, FERC authorized expansions of the Creole Trail Pipeline and the Sabine Crossing Pipeline, which will bring a new interstate natural gas line to the terminal. The plant is already large. Currently, Sabine Pass produces about 30 million tonnes a year, and Cheniere is the largest LNG exporter in the United States. As a result, the expansion would add roughly two-thirds again to the terminal’s current output.

Phase 1: Bechtel, Train 7, and the financing

Cheniere will build the expansion in phases. First, Phase 1 covers a single train, Train 7, with a boil-off gas re-liquefaction unit and tie-ins to the existing terminal. It would add more than 6 million tonnes a year, and the company says it has already sold that output on long-term contracts.

Cheniere has also lined up its contractor. On May 28, Cheniere signed a lump-sum, turnkey engineering, procurement, and construction (EPC) contract with Bechtel for Phase 1. At the same time, it issued a limited notice to proceed so early work could start. Since then, Cheniere has spent about $500 million on early works.

Meanwhile, the money is taking shape. Cheniere has secured financing for 50% of Phase 1. Typically, the company self-finances half of its expansions and borrows the other half from banks.

Cheniere Sabine Pass expansion

The expansion would add three liquefaction trains to the Sabine Pass terminal in Cameron Parish, Louisiana.

What happens next for Sabine Pass?

The next step is the investment decision. Cheniere President Zach Davis said earlier this month that, with commercial support, the EPC contract and financing commitments lined up, the company is well positioned to reach a final investment decision on Phase 1 in the coming months. That decision depends on final regulatory approvals, and the company earlier said it expected it by early 2027. Construction would then begin in earnest. Phase 1 is expected to add capacity in the early 2030s. The US LNG building boom is also moving elsewhere. For example, Worley has signed an EPC contract for Venture Global’s CP2 expansion in Louisiana, ahead of a final investment decision targeted for early 2027.

Other projects

Calcasieu Parish, Louisiana, is currently under construction on a major liquefied natural gas export complex, after the final investment decision in April 2025. Construction of the project is done in stages, the first three LNG trains are being constructed and site construction is in progress. Upon its completion, the plant is anticipated to contribute greatly to the U.S. LNG export capacity and also provide thousands of people with jobs in the course of the construction. It is one of the large-scale energy infrastructure developments in the United States.

Fact Sheet

Project: Sabine Pass Liquefaction (SPL) Expansion

Location: Cameron Parish, Louisiana, USA

Developer: Cheniere Energy

Capacity: up to about 20 million tonnes a year (three trains)

Phase 1: Train 7, more than 6 million tonnes a year

EPC contractor (Phase 1): Bechtel Energy (lump-sum, turnkey; signed May 28, 2026)

Regulatory approval: FERC, November 19, 2026

Early works spent: about $500 million

Financing secured: 50% of Phase 1

Final investment decision: expected in the coming months

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.