The San’ao Nuclear Power Plant in Zhejiang Province, China, has progressed significantly since construction began on Unit 1. Its first Hualong One reactor entered commercial operation on April 29, 2026.

The 1,116MW net-capacity reactor was connected to the national electricity grid on March 12, 2026, before completing commissioning tests, including a 168-hour continuous test run.

Meanwhile, Unit 2 has advanced through hot functional testing, a key stage before fuel loading, with electricity generation targeted for 2027.

Construction of Unit 3 also commenced in November 2025, following the first nuclear island concrete pour on December 19, 2025. The six-reactor development will use China’s domestically developed Hualong One (HPR1000) pressurised water reactor technology.

Once completed, the plant is expected to generate more than 54 billion kWh of electricity annually. This will support power demand across Zhejiang Province and the wider Yangtze River Delta while reducing reliance on coal-fired generation.

San'ao Nuclear Power Plant Advances as China Expands Hualong One Reactor Development

Construction Begins at SanAo Nuclear Power Plant, China

Reported August 14,2021 – Construction has officially begun at the San’ao nuclear power plant in Zhejiang Province, China. To mark the start, workers poured the first concrete for Unit 1’s nuclear island.

Furthermore, San’ao 1 will be the first of six Hualong One pressurised water reactors planned for the site. Also,China is advancing the Haiyang nuclear project through the construction of its fifth reactor.

Prior to construction, site surveys began 13 years earlier. Thereafter, the National Energy Administration approved the project in 2015. Following this approval, the State Council authorised the construction of Units 1 and 2 in December 2020.

In addition, the National Nuclear Safety Administration issued their construction permits on December 30. Consequently, Yuan Jiajun, Secretary of the Zhejiang Provincial Committee of the Communist Party of China and Director of the Standing Committee of the Provincial People’s Congress, ordered construction to begin the following day.

Also Read: China connects first Hualong One to grid.

San’ao Nuclear Power Plant Expands China’s Nuclear Capacity

With construction underway at the San’ao 1 nuclear power plant, China has seven Hualong One units under construction. Additionally, the projects include Fuqing 6, which was scheduled to enter commercial operation later in 2021. 

China National Nuclear Corporation(CNNC) is also constructing one unit (the first of two) at Taipingling in Guangdong and two at Zhangzhou in Fujian province. Additionally, China General Nuclear (CGN) is building two Hualong One reactors at its Fangchenggang site in Guangxi Province.

Meanwhile, the world’s first Hualong One reactor, Unit 5 at China National Nuclear Corporation’s (CNNC) Fuqing nuclear plant in Fujian Province, was connected to the grid in November.

CGN Party Secretary, Chairman and General Manager Yang Changli emphasised the company’s commitment to the San’ao nuclear power project. He stated that CGN would draw on more than 30 years of nuclear construction experience and its expertise in the Hualong One reactor.

Furthermore, the company would work with participating project units to uphold nuclear safety responsibilities and deliver high-quality construction.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *