Vantage Data Centers New £250 Million LHR21 Facility in London, UK

Home » Buildings » Data Center » Vantage Data Centers New £250 Million LHR21 Facility in London, UK

Vantage Data Centers’ £250 million LHR21 data center in Park Royal, West London, has been completed, with the main contractor, Glencar Construction, confirming completion on January 14, 2026.

The six-storey facility spans 194,000 sq ft (18,000 sq m) and provides 20MW of IT capacity. This is intended to support demand for high-density digital infrastructure in the London market.

Glencar delivered the civil, structural and mechanical, electrical and plumbing (MEP) works. Glencar also did partial technical fit-out designed to support phased occupation. Additionally, the project features infrastructure for future waste-heat recovery and a large facade artwork, 11 Million Dots, by artist Rafael El Baz.

11 Million Dots, by artist Rafael El Baz
11 Million Dots by Rafael El Baz

Vantage announced the facility’s opening in September 2025, marking a further expansion of its London operations. The completion continues to strengthens Vantage’s position in the UK data center market as operators seek to accommodate growing cloud and AI workloads within increasingly constrained urban sites.

This is as other developments such as Nscale’s £2bn AI data center project in Essex face uncertainty due to growing grid concerns in the UK.

LHR21 / LHR2

The LHR21 facility, also referred to as LHR2, is part of Vantage Data Centers’ second London campus located in the Park Royal district of West London. The data center covers 194,000 sq ft and has about 20 MW of IT load capacity.

Factsheet for LHR21 Facility for Vantage Data Centers in London

Developer and operator: Vantage Data Centers

Location: Park Royal, West London, UK

Floor Space: 194,000 sq ft (18,000 sq m)

IT Load Capacity: 20 MW

Investment: £250 million. Compare Equinix’s £3.9 billion data center on the DC01UK site in Hertfordshire, England.

Site Features: Six-story build, advanced cooling systems, sustainable design with BREEAM Excellent mark.

Key features: High-density IT infrastructure, rooftop cooling plant, emergency generators, partial technical fit-out and provision for future waste-heat recovery.

Status: Opened in September 2025

Construction completion: January 14, 2026

Project Team

Main contractor: Glencar Construction

Architect: studioNWA (Nicholas Webb Architects)

Structural engineer: Pinnacle Consulting Engineers

Structural steelwork: Caunton Engineering

Building services contractor: ESG

Additional project partner: BCS Consultancy

Project Timeline

April 2023: Vantage announces the second London campus (LHR2) with 20 MW capacity and £250 million investment.

April 2023: Glencar Construction awarded contract to build LHR21 facility.

September 2025: Vantage announces the LHR2 London campus will open end of September, including the LHR21 facility.

Vantage Data Centers New £250 Million LHR21 Facility in London, UK
Located near Heathrow Airport, the new 194,000-square-foot, six-story data center will supply online data services to various businesses and enterprises.

Plans Set for Construction of New LHR21 Facility for Vantage Data Centers in London

Reported April 27, 2023 – Contract for the construction of Vantage’s new data center in London has been awarded. The contract was awarded to Glencar, a leading construction delivery partner, growing to become one of the UK’s most successful privately-owned contractors.

Located close to Heathrow Airport, the new 194,000-square-foot, six-story data center will supply online data services to various businesses and enterprises. It is thus expected to generate 20 MW of output.

The 1.2-acre broader site campus is being prepared for construction by Glencar’s specialized data center team. The LHR21 facility for Vantage Data Centers in London is expected to complete in early 2025. The Glencar team also collaborated as part of the “Contractor Alliance” to complete LHR21 with Essex Services Group (ESG), a renowned leader in building services in the data center industry.

Read Also: Plans submitted for rental homes at Anderston Quay in Glasgow

Project Scope

The LHR21 facility for Vantage Data Centers in London will feature the most state-of-the-art electrical equipment. These will provide maximum efficiency and reliability, advanced cooling systems designed to be climate independent. This is also being environmentally responsible and physical and electronic security systems, including industry-leading security management.

Eddie McGillycuddy, CEO of Glencar, stated: “Securing this project with Vantage Data Centres is a real achievement for Glencar as we enter the Data Centre space. Many members of our team have extensive experience in this field. However, this is our first significant project under the Glencar name, and Vantage has been a fantastic partner from the beginning.”

“We developed a successful plan to carry out this project in London. Thanks to our involvement during the planning and pre-construction phases and our in-depth understanding of highly specialized industrial, pharmaceutical, and temperature-controlled facilities. In the upcoming weeks, we look forward to beginning our work with Vantage and on-site operations.”

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Posts

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *