An Arcadis and Egis joint venture will design the landside half of the Port of Montreal’s Contrecœur Container Terminal, a Quebec project whose estimated cost has climbed to C$2.3 billion and whose opening has slipped from 2024 to 2030. Marine works are already underway on the St. Lawrence River site.
DP World, which is set to operate the terminal for the Montreal Port Authority, appointed the pair as Operator’s Engineer. Their brief covers the buildings, container yard, rail yard, utilities and truck gates the terminal needs to run. Once complete, it will add 1.15 million twenty-foot equivalent units (TEUs) of annual capacity, lifting the port’s container capacity by about 60%.
Who Designs What?
Arcadis will lead the environmental assessment along with geotechnical and electrical engineering, rail infrastructure and the terminal’s main operations and administration buildings. Egis takes the utility buildings, civil utilities, crane rails, pavements and truck gate infrastructure.
Moffatt & Nichol joins as a subconsultant. It will set out terminal planning and operating specifications, which will shape the yard layout and how containers move through it.
Kevin Karaloff, who leads ports and marine work at Arcadis, described the scheme as a major investment in Canada’s trade infrastructure and an important step for one of the country’s key trade gateways.
How Did the Price Reach C$2.3 Billion?
When Ottawa authorized the terminal in 2021, the port authority aimed to open it by 2024. The cost estimate stood at C$1.6 billion before federal minister Dominic LeBlanc put the figure at C$2.3 billion in September 2025, as the port signed its development agreement with DP World’s Canadian unit.
Public money covers a large share. The Canada Infrastructure Bank is lending C$1.16 billion, with C$150 million from Transport Canada and C$130 million from the Government of Québec. Port officials said in August 2026 that 25% to 30% of the funding package was still to be confirmed, and talks on DP World’s contribution continue alongside its construction and operating agreement.
When Will the Terminal Open?
Operations are targeted for 2030. On the water, Contrecœur Terminal Constructors, owned 60% by Pomerleau and 40% by Aecon, holds a C$609 million design-build contract for dredging, quay walls and the berths. Prime Minister Mark Carney marked the start of construction at the Contrecœur terminal in April 2026, and the port confirmed in August that in-water work had begun.
The move downstream reflects a squeeze on the island. Transport Canada describes Montreal as the largest container port in Central and Eastern Canada, and the port authority says its existing terminals there are approaching full capacity, with little room left to grow.
The finished site will have two berths, a container yard, an intermodal rail yard linked to the CN network and a truck gate. Ottawa has designated it a project of national interest, and the federal government expects it to support about 4,000 jobs a year during construction and some C$750 million in annual economic benefits once running.
Detailed design is also the current stage for Mississauga’s Lakeshore Bus Rapid Transit project, where HDR and GEI Consultants are preparing a 2 km busway that city staff expect to cost about C$89 million, with early works planned for late 2026 or early 2027.