Project Factsheet: Dunbar Power Project in Fayette
- Project: Dunbar Power Project
- Site Area: 837 acres total
- Data Center Area: 28.3 million square feet
- Location: Dunbar Township, Fayette County, Pennsylvania
- Status: Proposed, FID targeted 2028
Project Team
- Developer: EmberClear, Houston, Texas
- Chief Engineer: Jim Palumbo
- Plant Landowner: Fay-Penn Business Council
- Data Center Parcel Owner: Bill Decenzo
- Grid Operator: PJM Interconnection
Scope
- 1.4 GW combined-cycle gas plant
- 137 acres for the plant site
- 650 acres reserved for data center
- Grid-bound electricity, not on-site supply
Project Highlights
- Gas hub links six major pipelines
- PJM Cycle 1 queue spot secured
- EPC contractor already lined up
- Both parcels carry M-1 zoning
Key Developments
- Proposal revealed last Thursday
- Supervisors cited blindside in post
- County board meets Dec. 11
- Air permitting already under way
Key Challenges
- No data center tenant secured
- Township relations need repair
- Investment decision waits until 2028
- Environmental reviews remain ahead
Outlook
- Commercial operation targeted Q2 2031
- Officials visit next month
- Ordinance discussion set Dec. 11
- Grid connection process advances