Project Factsheet: Cameron LNG Expansion by Sempra
LocationHackberry, Louisiana
DeveloperSempra Infrastructure
Project TypeLiquefied Natural Gas (LNG) Export Terminal
StatusFERC-approved; expansion timeline extended to 2033
Existing Capacity3 trains, 14.95 million tonnes per year
Expansion Capacity4th train, 6.75 million tonnes per year; total 21 million tonnes per year after expansion
TechnologyElectric-drive compressors for lower emissions, provisions for future carbon capture
Footprint500 acres
Workforce Impact
Peak construction 3,200 workers
Permanent jobs added 69
Strategic SignificanceMajor U.S. LNG export hub with room for future growth
Other Projects

Another major LNG project making headway is the Plaquemines LNG. The project is currently pursuing an $18 billion expansion that would make it North America’s largest liquefied natural gas export terminal under the Trump administration’s expedited “national energy emergency” permitting process. The facility is to be expanded from almost 590 acres to about 1,220 acres along the Mississippi River, more than doubling its size. The Plaquemines LNG expansion was approved by the Army Corps of Engineers in a matter of 10 days, instead of the usual 30-day public comment period. In the meantime, environmentalists say the expedited review could endanger up to 470 acres of wetlands and river bottoms in Central Plaquemines Parish in Louisiana.