Cape Station Geothermal Project Reaches First Power as 500MW Construction Advances in Utah

Home » Energy » Geothermal » Cape Station Geothermal Project Reaches First Power as 500MW Construction Advances in Utah
Cape Station Geothermal Project in Utah

Project Fact Sheet

ProjectCape Station geothermal power development

DeveloperFervo Energy

LocationBeaver County, near Milford, Utah, United States

TechnologyEnhanced Geothermal Systems (EGS)

Total planned capacityApproximately 500MW

Phase I:

  • Capacity: Approximately 100MW across three GeoBlocks
  • Status: First GeoBlock exporting electricity; remaining units undergoing commissioning
  •  Project financing: Approximately $421.4 million

Phase II:

  • Capacity: 400MW across eight 50MW GeoBlocks
  • Status: Construction and drilling underway
  • Target commercial operation: 2028

Google power purchase agreement396MW, with an option for approximately 600MW additional capacity

Other power buyersSouthern California Edison, Shell Energy and community choice aggregators

Drilling technologyHorizontal drilling, multi-stage stimulation and distributed fibre-optic sensing

Major equipment supplierBaker Hughes

Phase II drilling progressApproximately 18% as reported in November 2026

Primary purposeDeliver continuous, carbon-free electricity to the grid

Project Team

Developer and operatorFervo Energy

Power generation equipment supplierBaker Hughes

Drilling contractorHelmerich & Payne

Power offtakers:

  • Google
  • Southern California Edison
  • Shell Energy

Power generation equipment partnerTurboden

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *