Project Overview
- 150MW geothermal PPA for data center operations.
- Parties: Google, Ormat Technologies, NV Energy.
- Structured under NV Energy’s Clean Transition Tariff (CTT).
Location
- Nevada, United States.
Capacity
- Total: 150MW geothermal power.
- Clean, firm baseload supply.
Scope
- Multi-project geothermal portfolio.
- Projects added as they reach operations.
Timeline
- Approval expected: H2 2026.
- First power: 2028.
- Full rollout: 2028–2030.
Contract Terms
- Starts at first project operation.
- Duration: 15 years after final project online.
Key Developers / Contractors
- Off-taker: Google
- Developer: Ormat Technologies
- Utility: NV Energy
Technology
- Geothermal generation.
- Supports continuous data center loads.
Regulatory Status
- Subject to PUCN approval.
Related Developments
- 100MW geothermal deal with Fervo Energy (2024).
- 13MW PPA with Switch.
- Collaboration with Sage Geosystems.
Significance
- Expands clean energy for data centers.
- Improves grid reliability in Nevada.
Project Team
Ormat TechnologiesProject developer, owner, and operator responsible for designing, constructing, and operating the portfolio of new geothermal power facilities.
GoogleEnd-use corporate customer purchasing up to 150 MW of clean, around-the-clock electricity to power its Nevada data centers and AI infrastructure.
NV EnergyRegional electric utility providing the grid connection and executing the PPA alongside Ormat under its Clean Transition Tariff (CTT) framework.
Public Utilities Commission of Nevada (PUCN)State regulatory body responsible for reviewing and approving the PPA structure and CTT framework.