Greenvolt Breaks Ground on 100-MW Solar and 200-MWh Battery Project in New Mexico

Home » Energy » Solar » Greenvolt Breaks Ground on 100-MW Solar and 200-MWh Battery Project in New Mexico
Greenvolt breaks ground on a 100-MW solar and 200-MWh battery storage project in New Mexico, backed by a $190 million financing package.

Project Factsheet

  • Project: Alamogordo Solar Hybrid (Alamogordo Solar and Battery Storage Project)
  • Developer: Greenvolt Power
  • Location: Otero County, New Mexico, United States
  • Development milestone: Groundbreaking announced November 25, 2026
  • Solar generation capacity: 100 MWac
  • Battery discharge capacity: 50 MW
  • Battery energy storage capacity: 200 MWh
  • Battery duration: Four hours at rated 50 MW output
  • Stated project investment: More than $120 million
  • Financing package: $190 million (construction-to-term loan, bridge loan, and letters of credit)
  • Lenders: MUFG Bank and ING Capital
  • Solar and battery EPC contractor: CJR Renewables
  • Substation and switchyard contractor: Dashiell Corporation
  • Interconnection: Managed by Greenvolt Power
  • Electricity purchaser: Tri-State Generation and Transmission Association
  • PPA term: 20 years (2028 to 2048)
  • Expected completion: Summer 2028
  • Projected temporary construction employment: Approximately 371 direct jobs
  • Projected permanent employment: Approximately six positions

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *