Project Factsheet: Hermes 2 Demonstration Reactor
DeveloperKairos Power LLC
Project NameHermes 2 Demonstration System
LocationOak Ridge, Tennessee
Target Output50 megawatts
Target Launch Date2030
Core TechnologyAdvanced fluoride salt-cooled high-temperature reactor (KP-FHR) using molten salt instead of water
Offtake and Energy UsePower sold to Tennessee Valley Authority (TVA) to supply electricity for Alphabet Inc.’s Google data centers
Funding Summary ($643 Million Total)
- Private Funding ($368M): Led by Google Ventures, DCVC, and Samsung C&T Corp. ($70M)
- Public Funding ($275M): Financed by the U.S. Department of Energy (DOE)
- Primary Capital Allocation: Direct construction of Hermes 2, with additional capital earmarked for expanding manufacturing operations in New Mexico