The Ministry of Industry and Trade is considering a plan for the Ninh Thuan nuclear power plant to become operational after 2035. Also, on the other hand, it will significantly increase solar power, energy storage, and adjusting the scale of LNG gas-fired power plants to ensure supply amidst the risk of delays in many large power projects.
In the second round of proposed adjustments to the Power Development Plan VIII, the Ministry of Industry and Trade presented nine scenarios for power source development under high demand conditions and proposed selecting scenario KB2A as the main option.
New Operational Timeline Unveiled for Ninh Thuan 1
Regarding nuclear power, the Ministry of Industry and Trade plans for the Ninh Thuan 1 project to be operational in 2037-2038 and the Ninh Thuan 2 project in 2039-2040.
Also, specifically, the Ninh Thuan 1 project, invested by Vietnam Electricity Group , has submitted a pre-feasibility study to the Ministry of Finance. The capacity used in the calculations includes two generating units. Each boasts a capacity of 1,200 MW, in accordance with the technological solution of its partner Rosatom.
According to assessments by the Russian partner and the planning consultancy, the minimum time from the feasibility study to the plant’s operation is approximately 12 years. Based on this, Ninh Thuan 1 will start operations in 2037-2038. However, EVN is still proposing an earlier timeline, 2034-2035, if favorable conditions regarding mechanisms and policies are met.
The Ministry of Industry and Trade plans for the Ninh Thuan 1 project to be operational in 2037-2038.

Ninh Thuan 2 New Operational Timeline
For Ninh Thuan 2, the Vietnam National Energy Industry Corporation (Petrovietnam) is conducting a pre-feasibility study. Moreover, the proposed plan includes two generating units, each with a capacity of 1,455 MW, with a South Korean technology partner. The investor estimates the project could be operational in 2039-2040, while also proposing an earlier date of 2035-2036, subject to favorable conditions.
Previously, the revised Power Development Plan VIII, approved in February 2025, projected that the Ninh Thuan 1 and Ninh Thuan 2 nuclear power plants would be operational between 2030 and 2035, with a total capacity of approximately 4,000-6,400 MW.
Not only is the schedule being recalculated, but the long-term plan under scenario KB2A projects a nuclear power capacity of approximately 30,771 MW by 2050, with capital requirements for the period 2026-2050 estimated at around $187.3 billion.
Lastly, the Ministry of Industry and Trade proposes studying special mechanisms for investment, capital mobilization, human resource development, and infrastructure; promptly implementing projects in Ninh Thuan; and reviewing potential nuclear power development sites in the North to provide a stable and long-term base power source.