Al Kharaitiyat infrastructure project continues to reshape northern Doha as Qatar advances the final stages of one of its largest residential infrastructure programmes. The multi-package development has reached another milestone after the completion of its second construction package, while work continues on the remaining phases. Once fully delivered, the project will provide modern roads, utility networks and public infrastructure serving more than 5,300 residential plots, reinforcing Qatar’s long-term urban development strategy.
The Public Works Authority (Ashghal) confirmed that Package 2 reached completion during 2026. Meanwhile, contractors continue building the remaining packages, with the final phase expected to conclude later in the year. The programme remains one of the country’s priority infrastructure investments supporting residential expansion north of Doha.
The project also reflects the Gulf region’s sustained investment in strategic transport infrastructure. Likewise, Saudi Arabia is advancing the $5bn Asir-Jizan highway construction project, where three consortiums have submitted bids to develop a major transport corridor linking the Asir region with Jizan.
Al Kharaitiyat infrastructure project reaches another construction milestone
Ashghal announced the completion of Package 2 after delivering integrated road and utility infrastructure serving 1,514 residential plots. The completed works improve internal mobility while strengthening links with surrounding arterial roads.
The package includes approximately 46 kilometres of roads, three signalized intersections and four pedestrian crossings. Engineers also installed 2,643 street lighting poles and nearly 9,900 parking spaces to improve accessibility throughout the community.
The development further delivered around 85 kilometres of shared pedestrian and cycling paths, encouraging sustainable mobility across the neighborhoods. Landscaping covering approximately 37,500 square metres has also enhanced the public environment.
Beyond transport improvements, contractors completed 51 kilometres of surface and groundwater drainage networks, 21 kilometres of treated sewage effluent pipelines, 6.6 kilometres of potable water networks, 24.4 kilometres of electricity infrastructure, and 7.3 kilometres of telecommunications networks. These services will support future residential growth while improving infrastructure resilience.
Ashghal added that nearly 70% of construction materials originated from local manufacturers under its Taheel Initiative, supporting Qatar’s industrial sector while reducing reliance on imported products.

Al Kharaitiyat infrastructure project moves toward full completion
The overall programme consists of four coordinated construction packages designed to serve 5,384 residential plots. Package 3 reached completion during 2025, while construction continues on Packages 1 and 4.
Ashghal expects Package 4 to reach completion during the third quarter of 2026, bringing the development closer to full delivery. Upon completion, residents will benefit from upgraded roads, improved drainage, modern utility services and safer pedestrian infrastructure.
The programme supports Qatar National Vision 2030 by delivering infrastructure capable of accommodating future population growth. Improved connectivity will also enhance access to schools, healthcare facilities and commercial developments planned across northern Doha.
The project demonstrates Qatar’s continued investment in integrated urban infrastructure rather than isolated road construction. By combining transport, utilities and public amenities within a single programme, the development aims to improve long-term service delivery while creating more sustainable residential communities.

Project fact sheet
Name: Roads and Infrastructure Development Project in Al Kharaitiyat and Izghawa
Project value: Approximately QR1.27 billion (about $347 million) for Packages 2 and 3 combined
Location: Al Kharaitiyat and Izghawa, Doha, Qatar
Project owner: Public Works Authority (Ashghal)
Project type: Roads and integrated infrastructure development
Current status (2026): Package 2 completed; Packages 1 and 4 under construction; final package expected to finish in Q3 2026
Development programme: Four construction packages
Residential plots served: 5,384 upon full completion
Roads delivered in Package 2: Approximately 46km
Pedestrian and cycling paths: Approximately 85km
Parking spaces: Nearly 9,900
Street lighting poles: 2,643
Drainage network: 51km
Treated sewage effluent network: 21km
Potable water network: 6.6km
Electricity network: 24.4km
Telecommunications network: 7.3km
Landscaped areas: 37,500m²
Local content: Around 70% locally sourced construction materials
Project team
Project owner: Public Works Authority (Ashghal)
Implementing agency: Roads Projects Department, Ashghal
Programme lead: Eng. Abdullah Al Nuaimi, Head of Northern Areas Section
Project engineer: Eng. Jassim Kano
Package 2
- Contractor: UCC Infra-Road for Trading and Contracting (Urbacon/InfraRoad JV)
- Consultant: CEG International
Package 3
- Contractor: Al Ghanim–NICC Joint Venture
- Consultant: Parsons International
Funding: Government of Qatar
Delivery model: Multi-package public infrastructure development programme
Also Read: AIIB approves US $165.5m loan to improve roads in Uzbekistan
Project scope
The project scope includes a 35-km surface and groundwater drainage network, 22 km of Treated Sewerage Effluent (TSE) network along with a 12-km potable water network. In addition, new sewage pipelines along with a new system to ensure the flow distribution will be provided and connected with Qatar’s main sewage network, to provide proper protection for the entire area against flooding and excess rainfall.
Eng. Abdulla Al-Naemi further added that it has been planned that the project will use local materials and elements that will be supplied by local manufacturers. “These local materials include gabbro, lighting poles and luminaires, directional signs in addition to sewage, surface water and rain water drainage pipes, asphalt, concrete, rebar and prefabricated manholes. The project is also targeting to achieve 85% of local materials used in the construction works, in line with the Public Works Authority’s support to local manufacturers and Ta’heel initiative which was launched in 2017,” he affirmed.
The project construction works is divided into four geographical zones which will be carried out successively. The duration of each phase will be one year while the full completion of the project is scheduled for Q2 2024.
The Roads and Infrastructure in Al Kharaitiyat and Izghawa Project (Package 2) is being implemented by UrbaCon and InfraRoad Joint Venture, at a cost of approximately US $137m.

Leave a Reply