Kenya is advancing plans for a KSh90 billion ($692 million) liquefied natural gas (LNG) electricity generation power project in Mombasa following an agreement between Greek energy company Amaco Energy S.A. and Arise Integrated Industrial Platforms (Arise IIP) Kenya. The proposed development, known as Hercules, will provide dedicated electricity, cooling and digital infrastructure to support industrial operations, port activities and artificial intelligence (AI) data centers at the Coast Integrated Industrial Park in Dongo Kundu.
The project, valued at approximately KSh90 billion, will initially deliver 250 megawatts (MW) of electricity, with the potential to expand generation capacity to 1 gigawatt (GW) as demand increases. The development is intended to address the growing need for reliable, round-the-clock electricity among energy-intensive industries and digital infrastructure operators while reducing additional pressure on Kenya’s national electricity grid.
Amaco Hercules Power Project: Details and Infrastructure Scope
Project Hercules will integrate three major infrastructure components: LNG-based electricity generation, advanced cooling systems and specialized digital infrastructure for AI and hyperscale data centers.
The initial power-generation phase will use a floating power barge equipped with gas turbines to convert LNG into electricity. Amaco has an existing strategic cooperation agreement with US energy technology company GE Vernova, signed in August 2026, to supply gas turbines for the proposed facility. The partnership provides a technology framework for the power-generation component of the development.
Beyond electricity generation, the Amaco Hercules project will incorporate cooling infrastructure designed to support high-density computing operations. Its proposed system could also utilize cold energy associated with LNG processing and recover waste heat for freshwater production. This integration is intended to improve resource efficiency while providing the continuous cooling required by large-scale AI computing facilities.

The power system will operate independently of Kenya’s national electricity grid. This allows industrial and digital infrastructure customers to access dedicated electricity supplies. The development is also designed to accommodate a potential transition towards hydrogen and renewable energy as technologies and commercial conditions evolve.
Dongo Kundu Industrial Park to Benefit from the Development
The Amaco Hercules project will be integrated into Arise IIP Kenya’s 500-acre Coast Integrated Industrial Park (CIIP), located within the Dongo Kundu Special Economic Zone (SEZ), near the Port of Mombasa.
The industrial park is being developed as part of Kenya’s wider industrialization and export-manufacturing strategy under the Kenya-Afreximbank Country Program. Its proximity to the Port of Mombasa is also expected to facilitate the movement of raw materials, manufactured goods and other industrial cargo. This is while attracting investments in manufacturing, logistics and technology.
Mombasa’s international telecommunications infrastructure is another important consideration. The coastal city hosts seven submarine fiber-optic cable connections. This also provides international connectivity that could support the establishment of regional data centers and hyperscale computing facilities.
By combining dedicated electricity generation, cooling infrastructure, port access and international telecommunications connectivity, the development aims to establish an integrated industrial and digital infrastructure hub in coastal Kenya.
The Amaco Hercules project is also expected to generate more than 1,500 jobs during construction. Approximately 550 to 650 direct and indirect employment opportunities are also anticipated once operations start. These will include positions in power generation, cooling systems and digital infrastructure management.
Implementation and Next Steps at the Kenya LNG Power Project
Amaco Energy and Arise IIP Kenya signed their strategic partnership agreement in November 2026 to advance the proposed development. However, the agreement establishes a framework for project development and does not necessarily mean that construction has started.
The two companies will undertake technical, commercial, environmental, regulatory and financial assessments before proceeding with full implementation. Detailed engineering, financing arrangements, regulatory approvals and commercial agreements with prospective electricity consumers are important expected milestones.
Amaco’s CEO, Theodore Theodoropoulos, has indicated that the project could enter full operation within approximately 20 to 24 months. However, this remains a projected timeframe, with the implementation schedule dependent on the completion of the outstanding development requirements.
If implemented as planned, Hercules could strengthen Kenya’s ability to attract energy-intensive industrial investments and large-scale AI computing operations. It will also establish a dedicated power-generation model for the country’s expanding digital economy.

Hercules Integrated Power and Digital Infrastructure Project: Fact Sheet
Location: Dongo Kundu, Mombasa
Project developer: Amaco Energy
Development partner: Arise IIP Kenya
Project cost: KSh90 billion (approximately $692 million)
Initial generation capacity: 250 MW
Potential generation capacity: 1,000 MW
Power source: Liquefied natural gas (LNG)
Generation technology: Gas turbines and floating power barge
Technology partner: GE Vernova
Supporting infrastructure: Advanced cooling systems and AI data-center infrastructure
Industrial park: Coast Integrated Industrial Park (500 acres)
Construction employment: More than 1,500 jobs
Operational employment: 550-650 direct and indirect jobs
Implementation timeline: 20-24 months projected for full operation
Agreement: Partnership agreement signed in November 2026
Who is Involved in the Hercules LNG power project in Kenya?
-
Amaco Energy S.A. – Project developer and LNG power infrastructure provider.
-
Arise Integrated Industrial Platforms (ARISE IIP) Kenya – Industrial park developer and project development partner.
-
GE Vernova – Gas turbine technology and equipment partner.
-
Kenya Ports Authority (KPA) – Port infrastructure partner.
-
Special Economic Zones Authority (SEZA) – Regulatory and industrial-zone partner.