Project Factsheet: Savannah River plutonium plant
- Baseline Value: $23.5 billion (NNSA-confirmed)
- Completion Target: December 2038
- Location: Savannah River Site, South Carolina
- Capacity: At least 50 pits per year
- Status: Full construction authorized Oct. 15
Project Team
- Owner: US Department of Energy
- Manager: National Nuclear Security Administration
- Site Contractor: Savannah River Nuclear Solutions
- Building Design: Fluor Federal Services
- Glovebox Design: Merrick & Co.
- Watchdog: US Government Accountability Office
Scope
- Convert 400,000-square-foot MOX shell
- Produce 50-plus plutonium pits yearly
- Auxiliary facilities across 160 acres
- Underground utilities and infrastructure
Project Highlights
- $3.1 billion in early packages
- Baseline set at 60% design
- 243 of 320 glovebox awards issued
- 3,000-plus workers at peak
Key Developments
- Baseline approved on Oct. 15
- Final design completed pre-approval
- MOX shell cleared for conversion
- Separate line item since 2023
Key Challenges
- Cost more than doubles 2021 range
- GAO flags execution problems
- Portfolio carries $4.8 billion overruns
- Rework risk from early baseline
Outlook
- Construction expands across the site
- Pits targeted from 2038
- Fees tie to project outcomes
- Watchdog scrutiny continues