Melbourne Airport Expansion Locks In Qantas Backing for $4.5 Billion Terminal Program

Home » Transport » Airports » Melbourne Airport Expansion Locks In Qantas Backing for $4.5 Billion Terminal Program
Melbourne Airport Expansion Locks In Qantas Backing for $4.5 Billion Terminal Program

Project Fact Sheet

  • Project Name: Melbourne Airport international terminal expansion and third runway
  • Location: Melbourne Airport, Tullamarine, Victoria, Australia
  • Project Value: $4.5 billion for the terminal expansion, plus an estimated $3 billion for the third runway, per Melbourne Airport
  • Client and Owner: Australia Pacific Airports Corporation, under a 50 year Commonwealth lease
  • Anchor Airline Partner: Qantas Group, under a commercial agreement announced in July 2026
  • Key Components: Five widebody gates and five aircraft stands, enlarged check in hall with common user bag drops, expanded baggage reclaim and border processing space, new Qantas lounge above Terminal 2, 3,000 metre parallel runway
  • Procurement Model: Privately funded, staged delivery inside a live round the clock airport
  • Construction Start: Early runway works 2025, main runway construction 2026, terminal works from late 2026
  • Expected Completion: Runway open 2031, Qantas lounge complete 2029, terminal program staged over several years
  • Jobs Created: 51,000 jobs supported by the third runway project, per Melbourne Airport
  • Environmental Features: Noise Amelioration and Noise Sharing plans required under approval conditions, about 83 hectares of Grey Box Woodland permanently protected
  • Strategic Impact: Capacity for growth from about 36 million passengers in FY25 to around 76 million by 2042

Project Team

Frequently Asked Questions

How much does the Melbourne Airport expansion cost?The international terminal expansion is valued at $4.5 billion, with the third runway estimated separately at about $3 billion. Both are being funded by Melbourne Airport rather than government.

When will the Melbourne Airport third runway be completed?The third runway is scheduled to open in 2031, with main construction under way from 2026 after early works in 2025.

Who is building the Melbourne Airport expansion?No main works contractor has been publicly named for the terminal program, and Melbourne Airport says detailed design, architects and tenancy partners are still being finalised.

What will the Melbourne Airport expansion deliver for passengers? It adds five widebody gates and five aircraft stands, an enlarged check in hall with automated bag drops, more baggage carousels and border processing space, and a Qantas International Business Lounge above Terminal 2 due in 2029.

How many jobs will the Melbourne Airport expansion create?Melbourne Airport says the third runway project alone will support 51,000 jobs and add close to $6 billion a year to the Victorian economy once operational.

Source: constructionreviewonline.com All rights reserved. Unauthorized reproduction prohibited.

Featured Companies

Comments

Leave a Reply

Your email address will not be published. Required fields are marked *