Capital One Arena Renovation Project Factsheet
Project Overview
ProjectCapital One Arena Renovation
LocationWashington, DC
Total Investment: $800+ million
Public Funding$515 million
Private Funding$372.5 million (Monumental Sports)
Key Stakeholders
OwnerDC
OperatorMonumental Sports & Entertainment
Project ManagerCAA ICON
ArchitectGensler
General ContractorClark Construction

Timeline
Start DateDecember 19, 2024
Completion DateSummer 2027
Lease TermThrough 2050 (with extension options)
Capital One Arena Renovations Major Features
New exterior facade
Enhanced F Street entrance
United Globe Club (800-person capacity)
United Lounge (150-person capacity)
Upgraded athlete facilities
Modernized concessions
New People’s Plaza

Construction Approach
Six-phase implementation
Continuous operation during renovation
Minimal event disruption
Focus on behind-the-scenes work initially