North Field offshore project has entered a new contracting phase as QatarEnergy LNG seeks contractors for a potential $4 billion offshore engineering, procurement, construction and installation (EPCI) package. The competition targets compression infrastructure designed to sustain production from Qatar’s vast North Field, the world’s largest non-associated natural gas field.
The latest move involves the COMP6 package under the North Field Production Sustainability (NFPS) program. Contractor prequalification will help identify companies capable of delivering complex offshore facilities, connecting infrastructure and associated installation works.
The opportunity follows the appointment of Technip Energies for front-end engineering design (FEED) work on COMP6. The forthcoming EPCI phase will move the package towards detailed construction planning, equipment procurement, fabrication and offshore installation. However, QatarEnergy LNG has not yet awarded the main construction contract.
The latest competition also highlights Qatar’s continued investment in maintaining gas production from existing offshore reservoirs. Rather than developing an entirely separate field, the NFPS program focuses on sustaining output through additional compression capacity and supporting infrastructure.
North Field offshore project advances compression infrastructure
The COMP6 package forms part of a wider offshore program addressing declining reservoir pressure as gas extraction continues. Compression facilities help maintain pressure, enabling operators to move gas through existing production systems towards onshore processing facilities. Consequently, the project supports the long-term performance of Qatar’s established gas infrastructure.
The planned works include offshore compression facilities, supporting structures and modifications connecting new equipment to existing systems. Contractors will need to coordinate engineering, procurement, fabrication and offshore installation to deliver the package. Moreover, the marine environment will demand careful planning for heavy lifting, transport, structural integrity and installation sequencing.
Technip Energies secured the COMP6 FEED assignment in September 2026. Its engineering studies will establish the technical basis for the subsequent implementation phase. However, the detailed
The wider NFPS program has already produced several major offshore awards. In December 2025, QatarEnergy LNG awarded Saipem, working with China Offshore Oil Engineering Company (COOEC), the COMP5 EPCI contract. That package covers two offshore compression complexes, each weighing approximately 68,000 tones.
The COMP5 award demonstrates the scale of offshore structures required to sustain North Field production. Nevertheless, it is a separate package from COMP6, and its contractors should not be mistaken for confirmed bidders on the latest opportunity.
North Field offshore project supports Qatar’s LNG ambitions
Qatar’s broader North Field expansion combines offshore production infrastructure with new onshore liquefied natural gas facilities. The country aims to increase annual LNG export capacity from approximately 77 million tones to 142 million tones by 2030. This expansion includes the North Field East, North Field South and North Field West developments.
Meanwhile, the NFPS program focuses on maintaining production from the existing offshore gas reservoir. Its compression projects therefore serve a different purpose from new LNG trains, although both contribute to Qatar’s wider export strategy.
The COMP6 prequalification process marks an important step towards another major offshore construction opportunity. However, the estimated $4 billion value represents the potential EPCI package, not an awarded contract. QatarEnergy LNG must complete its procurement process before confirming the successful contractor and final commercial terms.
QatarEnergy’s project highlights the Gulf’s continued investment in large-scale natural gas infrastructure to strengthen long-term production capacity. Similarly, Sharjah National Oil Corporation has completed the first development phase of the Hadiba Gas Field Project, boosting domestic gas production and preparing for further expansion. Both developments reflect regional efforts to meet rising energy demand through new gas resources and supporting infrastructure.

Also read: $40bn North Field West Offshore Expansion Project Draws COOEC, L&T, McDermott, Saipem in Qatar
Project fact sheet
Name: North Field Production Sustainability (NFPS) COMP6 offshore compression facilities.
Location: North Field, offshore northeastern Qatar.
Client and project operator: QatarEnergy LNG.
Estimated EPCI contract value: Up to $4 billion.
Current stage: Contractor prequalification for the EPCI phase.
Previous engineering milestone: Technip Energies secured the FEED contract in September 2026.
Main construction scope: Offshore compression facilities, supporting structures and connections to existing production systems.
Primary objective: Sustain natural gas production and support gas transportation to onshore processing facilities.
Wider program: North Field Production Sustainability.
Related national development: Qatar’s North Field LNG expansion program.
Overall NFPS implementation: Planned in phases through 2032, according to available reporting.
Contract award status: No COMP6 EPCI contractor confirmed at the prequalification stage.
Project team
Client and operator: QatarEnergy LNG.
Parent Energy Company: QatarEnergy.
FEED contractor: Technip Energies.
EPCI contractor: To be determined through prequalification and procurement.
Offshore engineering and construction bidders: Not confirmed for COMP6.
Related NFPS COMP5 EPCI contractors: Saipem and China Offshore Oil Engineering Company (COOEC).
Onshore gas processing interface: QatarEnergy LNG’s existing North Field production and processing infrastructure.