Fact Sheet for the Crown Estate’s Celtic Sea Offshore Floating Wind Round 5
Leasing EntityThe Crown Estate
LocationCeltic Sea, off South Wales and South West England
Capacity PotentialUp to 4.5 GW across three projects each up to 1.5 GW
Seabed Area1,000 km2 across the three project sites
Developers:
- Equinor with 1.5 GW.
- Gwynt Glas wind project also with 1.5 GW
- Ocean Winds with the third 1.5 project site

Environmental Commitment:
- Multi-million-pound marine survey program.
- Up-front Habitats Regulation Assessment (HRA) also done to de-risk ecological impact.
Socioeconomic CommitmentJob creation and local economic growth. Crown Estate also says a ‘Supply Chain Accelerator’ fund has been launched.
Tender StructureThree Agreements for Lease to be awarded, totaling to 4.5 GW floating offshore wind development. The Crown Estate also limits bidders to winning only one project site.
Timeline of Key Events
December 2023Crown Estate announces Information Memorandum for Round 5.
January 2024Bidders Day held in Swansea.
February 2024Official Concession Notice for Round 5 announced.
August 2024Invitation to Tender Stage 1 begins.
Spring 2025‘Rising clock’ auction for the three project sites.
Summer 2025Signing of Agreements for Lease (AFLs) with successful bidders.
October 2025Equinor and Gwynt Glas enter into lease agreements with The Crown Estate.
November 2025Crown Estate announces award of rights to develop the third floating offshore wind site in the Celtic Sea to Ocean Winds.
Spring 2026Crown Estate expects to finalize an Agreement for Lease with Ocean Winds.